In: Operations Management
Dan's procurement team will release an order for pigments (i.e., one of the main ingredients for making paints) to meet the gross requirement over the next 5 weeks as indicated in the inventory status record below. The lead time for pigments is one week. Currently, there are 40K gallons of pigment on hand. Assuming that Dan's follows “Lot-for-lot” method to determine the lot size (i.e., order quantity), when and how much should Dan's order pigments?
Week | Week | Week | Week | Week | ||
On Hand | 1 | 2 | 3 | 4 | 5 | |
Gross Requirements | 75 | 50 | 70 | |||
Scheduled Receipts | ||||||
Projected Available Balance | 40 | |||||
Planned Order Releases |
The schedule and quantities would be as under:
Week |
Week |
Week |
Week |
Week |
||
On Hand |
1 |
2 |
3 |
4 |
5 |
|
Gross Requirements |
75 |
50 |
70 |
|||
Scheduled Receipts |
35 |
50 |
70 |
|||
Projected Available Balance |
40 |
40 |
0 |
0 |
0 |
0 |
Planned Order Releases |
35 |
50 |
70 |
Projected Available Balance = On hand inventory – requirement + Scheduled receipts
Eg.
Projected Available Balance for week 1 = 40-0+0 = 40
Projected Available Balance for week 2 = 40-75+35 = 0
Scheduled receipts = Quantity required to make the Projected Available Balance “nil”
Planned order release = quantity required as per the Scheduled receipt and defined lead time.
Lead time = 1 week (so Planned order release will happen in the 1 week prior to the scheduled receipt)
Planned order release will happen in Week 1, Week 3 and Week 4 for quantity 35, 50 and 70 respectively.
These would be delivered as scheduled receipts in Week 2, Week 4 and week 5.