In: Finance
1A) Your firm is evaluating a capital budgeting project. The
estimated cash flows appear below. The board of directors wants to
know the expected impact on shareholder wealth. Knowing that the
estimated impact on shareholder wealth equates to net present value
(NPV), you use your handy calculator to compute the value. What is
the project's NPV? Assume that the cash flows occur at the end of
each year. The discount rate (i.e., required rate of return, hurdle
rate) is 14.5%. (Round to nearest penny)
Year 0 cash flow | -122,000 |
Year 1 cash flow | 59,000 |
Year 2 cash flow | 43,000 |
Year 3 cash flow | 44,000 |
Year 4 cash flow | 43,000 |
Year 5 cash flow | 34,000 |
1B) What is the discount rate at which the following cash flows
have a NPV of $0? Answer in %, rounding to 2 decimals.
Year 0 cash flow = -145,000
Year 1 cash flow = 35,000
Year 2 cash flow = 42,000
Year 3 cash flow = 43,000
Year 4 cash flow = 30,000
Year 5 cash flow = 41,000
Year 6 cash flow = 42,000
ANSWER
Part 1:
NPV :
NPV is the difference between Present value of Cash Inflows and
Present value of cash outflows.
NPV = PV of Cash Inflows - PV of Cash Outflows
If NPV > 0 , Project can be accepted
NPV = 0 , Indifference point. Project can be accepted/
Rejected.
NPV < 0 , Project will be rejected.
Year | CF | PVF @14.5 % | Disc CF |
0 | $ (122,000.00) | 1.0000 | $ (122,000.00) |
1 | $ 59,000.00 | 0.8734 | $ 51,528.38 |
2 | $ 43,000.00 | 0.7628 | $ 32,798.76 |
3 | $ 44,000.00 | 0.6662 | $ 29,311.38 |
4 | $ 43,000.00 | 0.5818 | $ 25,017.65 |
5 | $ 34,000.00 | 0.5081 | $ 17,276.33 |
NPV | $ 33,932.50 |
NPV of Project is $ 33932.50
Part 2:
IRR :
IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash
Outflows or Rate of growth is expected from project/ Investment. At
IRR, NPV of Project/ Investment will be Zero. It assumes that
intermediary Cfs are reinvested at IRR only.
IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in disc rate ] * 1%
If IRR > Cost of Capital - Project can be accepted
IRR = Cost of Capital - Indifferebce Point - Project will be
accepted / Rejected
IRR < Cost of Capital - Project will be erejected
Year | CF | PVF @15 % | Disc CF | PVF @16 % | Disc CF |
0 | $ -145,000.00 | 1.0000 | $ -145,000.00 | 1.0000 | $ -145,000.00 |
1 | $ 35,000.00 | 0.8696 | $ 30,434.78 | 0.8621 | $ 30,172.41 |
2 | $ 42,000.00 | 0.7561 | $ 31,758.03 | 0.7432 | $ 31,212.84 |
3 | $ 43,000.00 | 0.6575 | $ 28,273.20 | 0.6407 | $ 27,548.28 |
4 | $ 30,000.00 | 0.5718 | $ 17,152.60 | 0.5523 | $ 16,568.73 |
5 | $ 41,000.00 | 0.4972 | $ 20,384.25 | 0.4761 | $ 19,520.63 |
6 | $ 42,000.00 | 0.4323 | $ 18,157.76 | 0.4104 | $ 17,238.57 |
NPV | $ 1,160.62 | $ -2,738.52 |
IRR = Rate at which least +ve NPV + [ NPV at that rate / Change
in NPV due to Inc of 1% in Int Rate ] * 1%
= 15 % + [ 1160.62 / ( 1160.62 - ( -2738.52) ) ] * 1 %
= 15 % + [ 1160.62 / ( 3899.14) ] * 1 %
= 15 % + [ 0.3 ] * 1 %
= 15 % + 0.3 %
= 15.30 %
At 15.30%, NPV will be Zero.