Pinnacle Inc. manufactures curtains to client specifications. It has two cost categories that are directly traced to its products: materials and labor. It also has estimated overhead that consists of:
Pinnacle is trying to calculate the cost of making Job #454, which includes:
The company also expects to use 23,136 labor hours for the year. If Pinnacle allocates overhead based on $250,000 estimated direct labor dollars, what is the total cost ofJob #454? *Hint, make a job order cost sheet for Job 454. It should include materials, labor, and overhead. Round each step to the nearest 2 decimal places. For your final answer, round to the nearest dollar.
| Total estimated overhead cost = 107344 + 122381 + 120476 | 350201 | 
| Predetermined overhead rate = Total estimated overhead cost / Estimated direct labor cost = 350201 / 250000 | 140.08% | 
| Job #454 | |
| Materials cost | 11387 | 
| Labor cost [ 33*12 ] | 396 | 
| Overhead cost [ 396 * 140.08% ] | 555 | 
| Total cost | 12338 |