In: Accounting
A project has an initial cost of $58,975, expected net cash inflows of $12,000 per year for 11 years, and a cost of capital of 10%. What is the project's NPV? (Hint: Begin by constructing a time line.) Do not round your intermediate calculations. Round your answer to the nearest cent.
The project's NPV is as follows:
Note: Project's NPV is calculating by constructing a time line.
Year | Annual Cash inflows | PV Factor @ 10% | Present value |
---|---|---|---|
1 | 12,000 | 0.90909 | 10,909.08 |
2 | 12,000 | 0.82645 | 9,917.40 |
3 | 12,000 | 0.75131 | 9,015.72 |
4 | 12,000 | 0.68301 | 8,196.12 |
5 | 12,000 | 0.62092 | 7,451.04 |
6 | 12,000 | 0.56447 | 6,773.64 |
7 | 12,000 | 0.51316 | 6,157.92 |
8 | 12,000 | 0.46651 | 5,598.12 |
9 | 12,000 | 0.42410 | 5,089.20 |
10 | 12,000 | 0.38554 | 4,626.48 |
11 | 12,000 | 0.35049 | 4,205.88 |
Total | $77,941 |
Net Present value (NPV) = Total Present value - Initial Investment cost
= $77,941 - $58,975
= $18,966
The project's NPV is $18,966