Question

In: Accounting

Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):

Molding Fabrication Total
Estimated total machine-hours used 2,500 1,500 4,000
Estimated total fixed manufacturing overhead $ 12,250 $ 16,350 $ 28,600
Estimated variable manufacturing overhead per machine-hour $ 2.30 $ 3.10
Job P Job Q
Direct materials $ 22,000 $ 12,500
Direct labor cost $ 28,200 $ 11,100
Actual machine-hours used:
Molding 2,600 1,700
Fabrication 1,500 1,800
Total 4,100 3,500

Sweeten Company had no underapplied or overapplied manufacturing overhead costs during the month.

Required:

For questions 1-9, assume that Sweeten Company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments and Job P included 20 units and Job Q included 30 units. For questions 10-15, assume that the company uses a plantwide predetermined overhead rate with machine-hours as the allocation base.

1. What were the company’s predetermined overhead rates in the Molding Department and the Fabrication Department? (Round your answers to 2 decimal places.)

2. How much manufacturing overhead was applied from the Molding Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.)

3. How much manufacturing overhead was applied from the Fabrication Department to Job P and how much was applied to Job Q? (Do not round intermediate calculations.)

4. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.)

5. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole dollar.)

6. What was the total manufacturing cost assigned to Job Q? (Do not round intermediate calculations.)

7. If Job Q included 30 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole dollar.)

8. Assume that Sweeten Company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. What selling price would the company have established for Jobs P and Q? What are the selling prices for both jobs when stated on a per unit basis? (Do not round intermediate calculations. Round your final answers to nearest whole dollar.)

9. What was Sweeten Company’s cost of goods sold for March? (Do not round intermediate calculations.)

10. What was the company’s plantwide predetermined overhead rate? (Round your answer to 2 decimal places.)

11. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? (Do not round intermediate calculations.)

12. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole dollar.)

13. If Job Q included 30 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole dollar.)

14. Assume that Sweeten Company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. What selling price would the company have established for Jobs P and Q? What are the selling prices for both jobs when stated on a per unit basis? (Do not round intermediate calculations. Round your final answers to nearest whole dollar.)

15. What was Sweeten Company’s cost of goods sold for March? (Do not round intermediate calculations.)

Solutions

Expert Solution

we will find Departmental Pre determined OH rate

1 ] Molding

Pre determined Oh rate = Fixed OH / Machine houre

=$12,250/2,500

=$4.9 fixed OH per machine hour

Total OH rate per Machine hour = Fixed OH + Variable OH

=$4.9+$2.30

=$7.2 per machine hour

Fabrication

$16,350/1500

=$10.9 per MH

Total OH rate =Fixed OH rate per MH+ Variable OH rate per MH

$10.9+$3.10

=$14 per machine hour

________________________________________________________________

2] Manufacturing OH applied Molding department = Rate per hour*Machine hour used

P Q
Molding $18,720[$7.2*2,600] $12,240[$7.2*1,700]

________________________________________________________________

3] Fabrication department applied OH = Rate per hour of fabricating department*Machine hour used in fabricating department

  • P Q
    Fabrication $21,000[$14*1,500] $25,200[$14*1,800]

________________________________________________________________

4]Now we will allocate cost to Product P

P
Direct material $22,000
Direct labor $28,200
Overhead applied
Modling departments $18,720
Fabrication department $21,000
Total manufacturing costs $89,920[$22,000+28,200+18,720+21,000]

____________________________________________________________________

5]

P
Direct material $22,000
Direct labor $28,200
Overhead applied
Modling departments $18,720
Fabrication department $21,000
Total manufacturing costs $89,920[$22,000+28,200+18,720+21,000]
units 20
Cost per unit $4,496[$89,920/20]

Sorry we can answer 4 parts per question only

Please upvote if you find this helpful.Incase of query please comment.


Related Solutions

Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March- Job P and Job Q. Job P was completed and sold by the end of the March and Job Q was incomplete at the end of the March. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT