In: Finance
Calculate the CPR and SMM using the 350% PSA schedule for months t=1 through t=30. Display your results in a table below with four columns labeled, from left to right, t, PSA, CPR, SMM.
The formula to calculate CPR and SMM are -
CPR = .06(n/30)*PSA
SMM = 1-(1-CPR) 1/12
Let's calculate these in excel -
t | PSA | CPR | SMM |
1 | 350% | 0.70% | 0.06% |
2 | 350% | 1.40% | 0.12% |
3 | 350% | 2.10% | 0.18% |
4 | 350% | 2.80% | 0.24% |
5 | 350% | 3.50% | 0.30% |
6 | 350% | 4.20% | 0.36% |
7 | 350% | 4.90% | 0.42% |
8 | 350% | 5.60% | 0.48% |
9 | 350% | 6.30% | 0.54% |
10 | 350% | 7.00% | 0.60% |
11 | 350% | 7.70% | 0.67% |
12 | 350% | 8.40% | 0.73% |
13 | 350% | 9.10% | 0.79% |
14 | 350% | 9.80% | 0.86% |
15 | 350% | 10.50% | 0.92% |
16 | 350% | 11.20% | 0.98% |
17 | 350% | 11.90% | 1.05% |
18 | 350% | 12.60% | 1.12% |
19 | 350% | 13.30% | 1.18% |
20 | 350% | 14.00% | 1.25% |
21 | 350% | 14.70% | 1.32% |
22 | 350% | 15.40% | 1.38% |
23 | 350% | 16.10% | 1.45% |
24 | 350% | 16.80% | 1.52% |
25 | 350% | 17.50% | 1.59% |
26 | 350% | 18.20% | 1.66% |
27 | 350% | 18.90% | 1.73% |
28 | 350% | 19.60% | 1.80% |
29 | 350% | 20.30% | 1.87% |
30 | 350% | 21.00% | 1.95% |