Question

In: Accounting

Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours.


Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours.

At the beginning of the year, the company estimated manufacturing overhead for the year would be $240,000 and estimated machine hours would be 10,000.

The following information pertains to December of the current year:


Job 10

Job 11

Job 12

Total


Work-in-process, Dec. 1

$16,000

$26,000

$38,000

$80,000


December production activity:








Materials requisitioned

$ 4,000

$ 4,800

$ 7,200

$16,000



Direct labor cost

$ 2,400

$ 3,600

$ 4,000

$10,000



Machine hours

400 hrs.

700 hrs.

900 hrs.

2000



Labor hours

120 hrs.

180 hrs.

200 hrs.

500












Actual manufacturing overhead cost incurred in December was $61,000.

Assuming Job 12 is the only job completed what is the cost assigned to ending work in process? Please show all computations.

Solutions

Expert Solution

predetermined overhead rate
240,000/10000
24 per machiner hrs
overhead applied = 24* mhrs actual
Job 10 Job11 Job12 Total
Work in process ,Dec 1 16,000 26,000 38,000 80,000
December activity
Direct materials 4,000 4,800 7,200 16,000
direct labor 2,400 3,600 4,000 10,000
overhead applied 9600 16800 21600 48000
total cost added in dec 16,000 25,200 32,800 74,000
total cost of job 32,000 51,200 70,800 154,000
WIP WIP finished goods
Cost assigned to Work in process inventory
32,000+51,200
83200 answer

Related Solutions

Basic Job Costing Project Reed Incorporated uses a job-order costing system and a predetermined overhead rate...
Basic Job Costing Project Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated manufacturing overhead for the year would be $240,000 and machine hours would be 8,000. The following information pertains to December of the current year: Job 10 Job 11 Job 12 Total Work-in-process, Dec. 1 $16,000 $26,000 $38,000 $80,000 The following transactions took place during the month of December: 1. Purchased raw...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 154,000 Fixed manufacturing overhead cost $ 655,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 100,000 Fixed manufacturing overhead cost $ 650,000 Variable manufacturing overhead cost per machine-hour $ 3.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 152,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.30 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 653,000 Variable manufacturing overhead cost per machine-hour $ 4.20 Required: A. Compute the plantwide predetermined overhead rate. B. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 656,000 Variable manufacturing overhead cost per machine-hour $ 5.00 Direct materials $ 310 Direct labor cost $ 300 Machine-hours used 35 QUESTION: If Moody uses a markup percentage of 130% of its total manufacturing cost, then what selling price per...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 160,000 Fixed manufacturing overhead cost $ 655,000 Variable manufacturing overhead cost per machine-hour $ 4.60 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 657,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 159,000 Fixed manufacturing overhead cost $ 653,000 Variable manufacturing overhead cost per machine-hour $ 4.10 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 156,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT