In: Accounting
The following data relate to direct materials costs for February:
Materials cost per yard: standard, $2.00; actual, $2.10
Standard yards per unit: standard, 4.5 yards; actual, 4.75 yards
Units of production: 9,500
Calculate the direct materials price variance.
a.$378.00 unfavorable
b.$1,795.50 favorable
c.$378.00 favorable
d.$4,512.50 unfavorable
Use this information for St. Augustine Corporation to answer the question that follow.
St. Augustine Corporation originally budgeted for $360,000 of fixed overhead at 100% of normal production capacity. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual fixed overhead was $360,000 and actual variable overhead was $170,000. Actual production was 11,700 units.
The fixed factory overhead volume variance is
a.$5,500 favorable
b.$9,000 unfavorable
c.$5,500 unfavorable
d.$9,000 favorable
Material Price Variance: | |||||||
(Standard Price-Actual Price)* Actual Quantity Used | |||||||
(2-2.10)*(9500*4.75) | |||||||
-4,512.50 | Unfavourable | ||||||
Answer is D | |||||||
Actual Units | 11,700.0 | Fixed OH Budgeted | 360,000.00 | ||||
Predetermined OH Rate | 30.0 | Units | 12,000.00 | ||||
OH Applied to Actual Work | 351,000.0 | Predetermined OH Rate | 30.00 | ||||
Fixed Overhead Volume Variance: | |||||||
(Budgeted Overhead-Applied Overhead) | |||||||
(360000-351000) | |||||||
9,000.0 | Unfavourable | ||||||
Answer is B | |||||||