Question

In: Finance

Scanlin, Inc., is considering a project that will result in initial aftertax cash savings of $2.1...

  1. Scanlin, Inc., is considering a project that will result in initial aftertax cash savings of $2.1 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debt–equity ratio of .80, a cost of equity of 11 percent, and an aftertax cost of debt of 4.6 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of +3 percent to the cost of capital for such risky projects. Under what circumstances should the company take on the project?

Solutions

Expert Solution

Solution) Debt-equity ratio = 0.80

D/E = 0.8

D = 0.8*E

Weight of debt (Wd) = D/(D + E) = 0.8E/(0.8E + E)

= 0.8/1.8 = 0.44444

Weight of equity (We) = E/(D+E) = E/(0.8E + E) = E/1.8E = 1/1.8 = 0.55556

The weighted average cost of capital (WACC) = Wd*Kd*(1- tax%) + We*Ke

Where Wd = Weight od debt

Kd*(1-tax%) = After-tax cost of debt = 4.6%

We = Weight of equity

Ke = Cost of equity = 11%

WACC = 0.44444*4.6% + 0.55556*11%

= 0.020444 + 0.061111

= 0.0815555

= 8.16%

Since management has applied an adjustment factor of +3%, so, weighted average cost of capital (WACC) = 8.16% + 3% = 11.16%

The company would receive initial after-tax cash savings of $2.1 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely.

The present value of the savings can be calculated using the Gordon Growth Model

= D1/(WACC - g)

D1 = Expected cash flow in year 1 = 2.1 million

WACC = 11.16%

g = growth rate = 2%

Thus, the present value of the savings = 2.1/(11.16% - 2%)

= 2.1/9.16%

= 22.925764

= 22.93 million or 22,925,764

The company should accept this project only when the present value of costs is less than the present value of after-tax savings, i.e.,

The present value of the costs < 22,925,764

Please comment in case of any doubts or clarifications required. Please Thumbs Up!!


Related Solutions

Scanlin, Inc. is considering a project that will result in initial aftertax cash savings of $2.1...
Scanlin, Inc. is considering a project that will result in initial aftertax cash savings of $2.1 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debut-equity ratio of 1.00, a cost of debt of 9.6 percent, and a beta of 1.50. The cost-saving proposal is closely related to the firm’s core business, so it is viewed as having the same risk as...
3) A company XYZ is considering a project which would result in an initial cash savings...
3) A company XYZ is considering a project which would result in an initial cash savings of $3.5 million at the end of the first year, and the savings will grow at the rate of 4 % per year, forever. The company has a target debt equity ratio of 0.55, the cost of equity is 13%, and the cost of debt is 5.5%. The cost saving proposal is riskier than the usual projects, so the firm uses an adjustment factor...
Project K has an initial required investment of $1,000,000. The project will result in operating cash...
Project K has an initial required investment of $1,000,000. The project will result in operating cash inflows of $200,000 per year for Years 1-3, $100,000 per year for Years 4-9, and have no cash flows in Year 10 and beyond. Calculate the payback period for Project K.
Ingram electric is considering a project with an initial cash outflow of $800000. this project is...
Ingram electric is considering a project with an initial cash outflow of $800000. this project is expected to have cash inflows of $350000 per year in year 1,2,3. the company has a wacc of 8.65% which is used as its reinvestment rate. whats the projects modified internal rate of return?
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow of $120 per week is anticipated from two stores that are being evaluated. Both stores have positive net present values. Site A Site B Probability Cash Flows Probability Cash Flows 0.2 60 0.2 30 0.2 120 0.1 60 0.3 130 0.2 120 0.3 150 0.2 150 0.3 180 a. Compute the coefficient of variation for each site. (Do not round intermediate calculations. Round your...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow of $160 per week is anticipated from two stores that are being evaluated. Both stores have positive net present values. Site A Site B Probability Cash Flows Probability Cash Flows 0.2 70 0.1 50 0.2 160 0.2 80 0.3 170 0.2 160 0.3 210 0.4 210 0.1 230 a. Compute the coefficient of variation for each site. (Do not round intermediate calculations. Round your...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow of $120 per week is anticipated from two stores that are being evaluated. Both stores have positive net present values.    Site A Site B Probability Cash Flows Probability Cash Flows .2 70 .1 40 .3 120 .2 70 .3 130 .2 120 .2 155 .4 150 .1 180 a. Compute the coefficient of variation for each site. (Do not round intermediate calculations. Round...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow...
Kyle’s Shoe Stores Inc. is considering opening an additional suburban outlet. An aftertax expected cash flow of $120 per week is anticipated from two stores that are being evaluated. Both stores have positive net present values.    Site A Site B Probability Cash Flows Probability Cash Flows .2 60 .2 30 .2 120 .1 60 .3 130 .2 120 .3 150 .2 150 .3 180 a. Compute the coefficient of variation for each site. (Do not round intermediate calculations. Round...
You are considering a project with an initial cash outlay of ​$70,000 and expected free cash...
You are considering a project with an initial cash outlay of ​$70,000 and expected free cash flows of ​$28,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
You are considering a project with an initial cash outlay of ​$72,000 and expected cash flows...
You are considering a project with an initial cash outlay of ​$72,000 and expected cash flows of ​$22,320 at the end of each year for six years. The discount rate for this project is 10.5 percent. a.  What are the​ project's payback and discounted payback​ periods? b.  What is the​ project's NPV? c.  What is the​ project's PI? d.  What is the​ project's IRR? a.  The payback period of the project is nothing years.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT