Question

In: Statistics and Probability

A production plant cost-control engineer is responsible for cost reduction. One of the costly items in...

A production plant cost-control engineer is responsible for cost reduction. One of the costly items in his plant is the amount of water used by the production facilities each month. He decided to investigate water usage by collecting seventeen observations on his plant's water usage and other variables.

Variable               Description

Temperature     Average monthly temperate (F)

Production          Amount of production (M pounds)

Days                      Number of plant operating days in the month

Persons                Number of persons on the monthly plant payroll

Water                   Monthly water usage (gallons)

Temperature

Production

Days

Persons

Water

58.8

7107

21

129

3067

65.2

6373

22

141

2828

70.9

6796

22

153

2891

77.4

9208

20

166

2994

79.3

14792

25

193

3082

81.0

14564

23

189

3898

71.9

11964

20

175

3502

63.9

13526

23

186

3060

54.5

12656

20

190

3211

39.5

14119

20

187

3286

44.5

16691

22

195

3542

43.6

14571

19

206

3125

56.0

13619

22

198

3022

64.7

14575

22

192

2922

73.0

14556

21

191

3950

78.9

18573

21

200

4488

79.4

15618

22

200

3295

i. Create the Scatter Plot graph between “water” and “production

ii. Use the appropriate routine of Data Analysis in MS Excel or any other statistical software in order to estimate the correlation matrix of all variables

iii. Compute 95% confidence interval for the values of the correlation coefficient between and determine which ones are statistically significant”

Solutions

Expert Solution

i. Create the Scatter Plot graph between “water” and “production

ii. Use the appropriate routine of Data Analysis in MS Excel or any other statistical software in order to estimate the correlation matrix of all variables

Temperature Production Days Persons Water
Temperature 1.000
Production -.024 1.000
Days .438 .106 1.000
Persons -.082 .918 .032 1.000
Water .286 .631 -.089 .413 1.000
17 sample size
± .482 critical value of r .05 (two-tail)
± .606 critical value of r .01 (two-tail)

iii. Compute 95% confidence interval for the values of the correlation coefficient between and determine which ones are statistically significant”

The significant correlations are:

(i) Persons & Production

(ii) Water & Production


Related Solutions

A production plant cost-control engineer is responsible for cost reduction. One of the costly items in...
A production plant cost-control engineer is responsible for cost reduction. One of the costly items in his plant is the amount of water used by the production facilities each month. He decided to investigate water usage by collecting seventeen observations on his plant's water usage and other variables. Variable               Description Temperature     Average monthly temperate (F) Production          Amount of production (M pounds) Days                      Number of plant operating days in the month Persons                Number of persons on the monthly plant payroll Water                  ...
You are the test engineer responsible for the final production testing of an automobile (VW Golf...
You are the test engineer responsible for the final production testing of an automobile (VW Golf R 2018) - create a list of tests with specifications as well as a block diagram depicting your test plan and the order in which you plan to test the car.  
A quality control engineer is interested in estimating the proportion of defective items coming off a...
A quality control engineer is interested in estimating the proportion of defective items coming off a production line. In a sample of 255 items, 45 are defective. Calculate a 95.0% confidence interval estimate for the proportion of defectives from this production line. (Use 3 decimal places in calculations and in reporting your answers.) Lower Limit: Upper Limit:
One of the most costly types of assets for any company is its property, plant, and...
One of the most costly types of assets for any company is its property, plant, and equipment. Select a company, or industry, of your choice and identify 2 common fixed assets they have (buildings, machines, etc). What causes these assets to depreciate and in what manner should it be recorded?
The quality-control inspector of a production plant will reject a batch of syringes if two or...
The quality-control inspector of a production plant will reject a batch of syringes if two or more defective syringes are found in a random sample of nine syringes taken from the batch. Suppose the batch contains 1% defective syringes. (a) Make a histogram showing the probabilities of r = 0, 1, 2, 3, , 8 and 9 defective syringes in a random sample of nine syringes. (b) Find μ. What is the expected number of defective syringes the inspector will...
QUESTION 1) You are an engineer and its know that your project /activities plant production had...
QUESTION 1) You are an engineer and its know that your project /activities plant production had cause an adverse health safety and environmental (HSE) impact. To improve the (HSE) quality, you have to cease your project activities or production for a period, resulting in the inability to meet the schedule and targets. how would you handle in a situation where there is a conflict between the IEM Regulation on Professional conduct and commercial consideration? Question 2) Engineers are often entrusted...
Lease analysis As part of its overall plant modernization and cost reduction program, the management of...
Lease analysis As part of its overall plant modernization and cost reduction program, the management of Tanner-Woods Textile Mills has decided to install a new automated weaving loom. In the capital budgeting analysis of this equipment, the IRR of the project was 25% versus a project required return of 11%. The loom has an invoice price of $260,000, including delivery and installation charges. The funds needed could be borrowed from the bank through a 4-year amortized loan at a 9%...
As part of its overall plant modernization and cost reduction program, the management of Tanner-Woods Textile...
As part of its overall plant modernization and cost reduction program, the management of Tanner-Woods Textile Mills has decided to install a new automated weaving loom. In the capital budgeting analysis of this equipment, the IRR of the project was 25% versus a project required return of 11%. The loom has an invoice price of $270,000, including delivery and installation charges. The funds needed could be borrowed from the bank through a 4-year amortized loan at a 9% interest rate,...
One of the most useful applications of oxidation-reduction reactions is the production of electricity. Batteries are...
One of the most useful applications of oxidation-reduction reactions is the production of electricity. Batteries are “prepackaged” redox reactions which produce electricity. Consider the redox reaction of aluminum metal reacting with vinegar (acetic acid). 2 Al + 6 HC2H3O2 º 2 Al(C2H3O2 )3 + 3 H2 or 2 Al + 6 H+ º 2 Al3+ + 3 H2 A battery works by physically separating the oxidation and the reduction half reactions. Why does the cardboard need to be soaked in...
Which of the following is a controllable cost for a plant supervisor? a.salaries of production supervisors...
Which of the following is a controllable cost for a plant supervisor? a.salaries of production supervisors b.None of these choices are correct. c.the use of direct materials d.the cost of insurance related to property, plant, and equipment
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT