All buildings must conform to code requirements including:
This code analysis is normally performed in a sequence of:
1,2,5,3,4,6 |
||
1,4,3,2,5,6 |
||
1,5,3,2,4,6 |
||
1,2,3,4,5,6 |
Answer : Correct Option C 1, 5, 3, 2, 4, 6
This code analysis is normally performed in a sequence of: Option C: 1, 5, 3, 2, 4, 6 as below
Thus the correct sequence will be as below
1 – Zoning ordinance permitted uses
5 – Zoning code required appearance and technical characteristics
3 – Building code occupancy groups
2 – Building code permitted height and area
4 – Building code permitted fire resistant structural capacity.
6 - Mechanical and electrical design.
The first things is the zone related activities needs to be completed so thatw e are free from zonal activities for the building work. Hence code 1 is the first sequence and code 5 is the second sequence.
After zonal, we need to move to building code i.e. Code 3.
After building code 3, we should have the code as building code for heinght and area i.e. code 2
After code 2, we should have code 4 – fire resistant structural capcity.
Finally last code 6 – mechanical and electrical design.