Question

In: Mechanical Engineering

Five mutually-exclusive projects consisting of reinforcing dams, levees, and embankments are available for funding by a...

Five mutually-exclusive projects consisting of reinforcing dams, levees, and embankments are available for funding by a certain public agency. The following tabulation shows the equivalent annual benefits and costs for each: Project Annual Benefits Annual Costs A $1,800,000 $2,000,000 B $5,600,000 $4.200,000 C $8,400,000 $6,800,000 D $2,600,000 $2,800,000 E $6,600,000 $5,400,000 Assume that the projects are of the type for which the benefits can be determined with considerable certainty and that the agency is willing to invest money in any project as long as the B-C ratio is at least one. Determine the annual worth (AW) of the best project that the public agency will select. The agency’s MARR is 10 % per year and the project lifetimes are each 15 years.

Solutions

Expert Solution

Project

Annual Benefits

Annual Costs

A

1,800,000

2,000,000

B

5,600,000

4,200,000

C

8,400,000

6,800,000

D

2,600,000

2,800,000

E

6,600,000

5,400,000

As equivalent annual benefits and annual cost of each project is provided. First, calculate B/C ratio to find the highest value for a project. Select the project on the basis of B/C ratio and then find the present worth of selected project on the basis of (P/A, 10%, 15 Year).

Calculate B-C ratio of project A -

Annual benefits = $1,800,000

Annual costs = $2,000,000

B-C ratio = Annual benefits/Annual costs = $1,800,000/$2,000,000 = 0.90

The B-C ratio of Project A is 0.90.

Calculate B-C ratio of project B -

Annual benefits = $5,600,000

Annual costs = $4,200,000

B-C ratio = Annual benefits/Annual costs = $5,600,000/$4,200,000 = 1.33

The B-C ratio of Project B is 1.33.

Calculate B-C ratio of project C -

Annual benefits = $8,400,000

Annual costs = $6,800,000

B-C ratio = Annual benefits/Annual costs = $8,400,000/$6,800,000 = 1.24

The B-C ratio of Project C is 1.24.

Calculate B-C ratio of project D -

Annual benefits = $2,600,000

Annual costs = $2,800,000

B-C ratio = Annual benefits/Annual costs = $2,600,000/$2,800,000 = 0.93

The B-C ratio of Project D is 0.93.

Calculate B-C ratio of project E -

Annual benefits = $6,600,000

Annual costs = $5,400,000

B-C ratio = Annual benefits/Annual costs = $6,600,000/$5,400,000 = 1.22

The B-C ratio of Project E is 1.22.

It has been stated that the agency is willing to invest money in any project as long as the B-C ratio is at least one. The B-C ratio of project A and D are less than 1. So, they will not be considered. Out of remaining three projects, B-C ratio is highest in the case of Project B.

Hence, Project B will be selected.

Annual worth of the project B = -(Annual cost)+annual benefit (P/A, 10%, 15 year)

Annual benefits = $5,600,000

Annual costs = $4,200,000

Annual worth=-(4, 200,000) + 5, 600,000(P/A, 10%, 15 year)

                     =4,200,000

So, Annual worth of the project in which company will invest is $4,200,000.


Related Solutions

Strand Plc has the following two mutually exclusive projects available to invest in. the discount rate...
Strand Plc has the following two mutually exclusive projects available to invest in. the discount rate is 10%. Each project can be undertaken only once. Cash flows Project Initial cost Year 1    Year 2 Year 3 1 (500) 400    200    100 2 (1000) 500    400 500 Required: (a) Calculate the payback period for each of the projects. Based upon the payback criterion which project should be chosen? (b) Calculate the net present value (NPV) of each...
QUESTION TWO [30] The following 2 mutually exclusive projects (Project A and Project B) are available...
QUESTION TWO [30] The following 2 mutually exclusive projects (Project A and Project B) are available to Simonsbosch Farm. They are producers of Rooi Bos tea. The initial cash outlay and cash flows are shown below and Simonsbosch will use straight line depreciation over each of the assets 4 year life and there will be no residual value on either investment. Years Cash Flows (A) Cash Flows (B) 0 (Investment) -240 000 -90 000 1 28 000 40 000 2...
Seether inc has the following two mutually exclusive projects available. What is the crossover rate for...
Seether inc has the following two mutually exclusive projects available. What is the crossover rate for these two projects? What is the NPV of each project at the crossover rate? Year Project R Project S 0 -45000 -76000 1 17000 20000 2 19000 20000 3 21000 35000 4 9000 30000 5 7000 10000
What does it mean for projects to be mutually exclusive? How should managers rank mutually exclusive...
What does it mean for projects to be mutually exclusive? How should managers rank mutually exclusive projects?
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 14 percent. Year          Project F         Project G 0 –$133,000    –$203,000    1 61,000    41,000    2 49,000    56,000    3 59,000    89,000    4 54,000    119,000    5 49,000    134,000    a. Calculate the payback period for both projects. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Calculate the NPV for...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 10 percent. Year Project F Project G 0 −$195,000 −$298,000 1 98,400 71,600 2 86,300 94,500 3 81,600 123,600 4 72,000 166,800 5 64,800 187,200 Calculate the payback period for both projects. Calculate the NPV for both projects. Which project, if any, should the company accept?
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm'swarehouse capacity. The relevant cash flows for the projects are shown in the following​ table: Initial investment        $500,000         $320,000 Year                 1          $130,000         $130,000 2          $120,000         $120,000 3          $130,000         $105,000 4          $200,000         $90,000 5          $250,000         $40,000 The​ firm's cost of capital is 17​%. a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b.  Which project is​ preferred?
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
IRRlong dash—Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive...
IRRlong dash—Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the firm's warehouse capacity. The relevant cash flows for the projects are shown in the following table: LOADING... . The firm's cost of capital is 1313 %. a. Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b. Which project is preferred? Project X Project Y Initial investment ​(CF 0CF0​)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT