Question

In: Finance

A proposed cost-saving device has an installed cost of $660,000. The device will be used in...

A proposed cost-saving device has an installed cost of $660,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $51,500, the marginal tax rate is 34 percent, and the project discount rate is 13 percent. The device has an estimated Year 5 salvage value of $76,500. What level of pretax cost savings do we require for this project to be profitable? Pretax savings $

Solutions

Expert Solution

The project should have atleast an NPV of 0.
The present value of known cash flows are:
1] Installed cost of the device $            6,60,000
Increase in NWC $               51,500
Initial cost $            7,11,500
2] PV of depreciation tax shield [calculations given in table below] = $            1,77,535
Year Depreciation % Depreciation Tax shield on depreciation at 34% PVIF at 13% PV at 13%
1 33.33 $         2,19,978 $           74,793 0.88496 $        66,188
2 44.45 $         2,93,370 $           99,746 0.78315 $        78,116
3 14.81 $             97,746 $           33,234 0.69305 $        23,033
4 7.41 $             48,906 $           16,628 0.61332 $        10,198
PV of depreciation tax shield $    1,77,535
3] PV of terminal non-operating cash flows:
After tax salvage value = 76500*(1-34%) = $               50,490
Recapture of net working capital $               51,500
Terminal non operating cash flows $            1,01,990
PV = 101900/1.13^5 = $               55,307
4] For NPV of 0, PV of after tax annual cost savings should be:
= 711500-177535-55307 = $            4,78,658
Annual after tax cost savings = 478658*0.13*1.13^5/(1.13^5-1) = $            1,36,089
Annual pre tax cost savings = 136089/(1-34%) = $            2,06,195 [Minimum]
CHECK FOR 0 NPV: 0 1 2 3 4 5
Annual pre tax cost savings = 136089/(1-34%) = $         2,06,195 $       2,06,195 $    2,06,195 $    2,06,195 $     2,06,195
Depreciation $         2,19,978 $       2,93,370 $        97,746 $        48,906 $                  -  
Incremental NOI $           -13,783 $         -87,175 $    1,08,449 $    1,57,289 $     2,06,195
Tax at 34% $              -4,686 $         -29,640 $        36,873 $        53,478 $        70,106
Incremental NOPAT $              -9,097 $         -57,536 $        71,576 $    1,03,811 $     1,36,089
Add: Depreciation $         2,19,978 $       2,93,370 $        97,746 $        48,906 $                  -  
Incremental OCF $         2,10,881 $       2,35,835 $    1,69,322 $    1,52,717 $     1,36,089
Capital expenditure $            6,60,000
Change in NWC $               51,500 $       -51,500
After tax salvage value = 76500*(1-34%) = $        50,490
FCF $          -7,11,500 $         2,10,881 $       2,35,835 $    1,69,322 $    1,52,717 $     2,38,079
PVIF at 13% [PVIF = 1/1.13^t] 1 0.88496 0.78315 0.69305 0.61332 0.54276
PV at 13% $          -7,11,500 $         1,86,621 $       1,84,693 $    1,17,349 $        93,664 $     1,29,220
NPV $                        46
Almost 0 [Difference due to approximation]

Related Solutions

A proposed cost-saving device has an installed cost of $800,000. The device will be used in...
A proposed cost-saving device has an installed cost of $800,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $81,000, the marginal tax rate is 23 percent, and the project discount rate is 8 percent. The device has an estimated Year 5 salvage value of $124,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $815,000. The device will be used in...
A proposed cost-saving device has an installed cost of $815,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $87,000, the marginal tax rate is 21 percent, and the project discount rate is 11 percent. The device has an estimated Year 5 salvage value of $133,000. What level of pretax cost savings do we require for this project to be profitable? What...
A proposed cost-saving device has an installed cost of $705,000. The device will be used in...
A proposed cost-saving device has an installed cost of $705,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $115,000, the marginal tax rate is 22 percent, and the project discount rate is 13 percent. The device has an estimated Year 5 salvage value of $86,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $725,000. The device will be used in...
A proposed cost-saving device has an installed cost of $725,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $135,000, the marginal tax rate is 21 percent, and the project discount rate is 13 percent. The device has an estimated Year 5 salvage value of $98,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $585,000. The device will be used in...
A proposed cost-saving device has an installed cost of $585,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $45,000, the marginal tax rate is 35 percent, and the project discount rate is 12 percent. The device has an estimated Year 5 salvage value of $65000.    Required: What level of pretax cost savings do we require for this project...
A proposed cost-saving device has an installed cost of $820,000. The device will be used in...
A proposed cost-saving device has an installed cost of $820,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $89,000, the marginal tax rate is 22 percent, and the project discount rate is 8 percent. The device has an estimated Year 5 salvage value of $136,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
a proposed cost-saving device has an installed cost of 725000. The device will be used in...
a proposed cost-saving device has an installed cost of 725000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is 135000, the marginal tax rate is 21 percent, and the,project discount rate is 13 percent. The,device has an estimated Year 5 salvage value of 98000. what level of pretax cost saving do,we require for this project to be profitable? yr                 3 yr              5...
A proposed cost- saving device has an installed cost of $735,000. The device will be used...
A proposed cost- saving device has an installed cost of $735,000. The device will be used in a five year project but is classified as a three year MACR property for tax purposes. The required initial net working capital investment is $55,000, the tax rate is 22 percent and the project discount rate is 9 percent. The device has an estimated Year 5 salvage value of $85,000. What level of pretax cost savings do we require for this project to...
A proposed cost-saving device has an installed cost of $790,000. The device will be used in...
A proposed cost-saving device has an installed cost of $790,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $77,000, the marginal tax rate is 21 percent, and the project discount rate is 10 percent. The device has an estimated Year 5 salvage value of $118,000. What level of pretax cost savings do we require for this project to be profitable? MACRS...
A proposed cost-saving device has an installed cost of $664,000. The device will be used in...
A proposed cost-saving device has an installed cost of $664,000. The device will be used in a five-year project but is classified as three-year MACRS (MACRS Table) property for tax purposes. The required initial net working capital investment is $53,500, the marginal tax rate is 34 percent, and the project discount rate is 13 percent. The device has an estimated Year 5 salvage value of $78,500. What is the depreciation each year of the project? What is the aftertax salvage...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT