Question

In: Accounting

Holl Corporation has provided the following data for November. Denominator level of activity 5,500 machine-hours Budgeted...

Holl Corporation has provided the following data for November. Denominator level of activity 5,500 machine-hours Budgeted fixed manufacturing overhead costs $ 68,750 Standard machine-hours allowed for the actual output 5,800 machine-hours Actual fixed manufacturing overhead costs $ 67,650 Required: a. Compute the budget variance for November. b. Compute the volume variance for November. (Input all amounts as positive values.)

Budget Variance: ______ ______

Volume Variance: _______ _______

Solutions

Expert Solution

Answer :-

Given date tabulated as follows :-

Particulars Budgeted Actual
Fixed manufacturing Overhead ($) $68,750 $67,650
Machine hours 5,500 5,800

Computation of budget variance for the November month.

Fixed overhead Budget variance = Budgeted fixed overhead - actual fixed overhead

=$68,750 - $67,650

= $1,100 (F).

# Calculation of volume variance :-

Fixed over head volume variance = applied fixed overhead - budgeted fixed overhead.

Standard fixed over head rate per hour = Budgeted fixed over head ÷ Standard machine hours

= $68,750 ÷ 5500 hours

= $ 12.50 per hour.

Applied fixed overhead = standaard fixed over head rate per hour × Actual machine hours

= $12.50 per hour × 5800 hours

= $ 72,500.

Budgeted fixed overhead = $68750. (Given)

Fixed over head volume variance = $72,500 - $68,750

= $3,750 favourable

# Budgeted fixed overhead volume variance =

$3,750 favourable.

----The End --


Related Solutions

Holl Corporation has provided the following data for November. Denominator level of activity 4900 machine-hours Budgeted...
Holl Corporation has provided the following data for November. Denominator level of activity 4900 machine-hours Budgeted fixed manufacturing overhead costs $ 58,310 Standard machine-hours allowed for the actual output 5200 machine-hours Actual fixed manufacturing overhead costs $ 57,330 Required: Calculate the following. Input all amounts as positive values FOH Budget Variance $ FOH Volume Variance $
1. Holl Corporation has provided the following data for November. Denominator level of activity 5,700 machine-hours...
1. Holl Corporation has provided the following data for November. Denominator level of activity 5,700 machine-hours Budgeted fixed manufacturing overhead costs $ 72,390 Standard machine-hours allowed for the actual output 6,000 machine-hours Actual fixed manufacturing overhead costs $ 71,250 Required: a. Compute the budget variance for November. b. Compute the volume variance for November. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,100 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,100 machine-hours Variable overhead costs: Supplies $ 15,810 Indirect labor 27,900 Fixed overhead costs: Supervision 17,000 Utilities 6,500 Depreciation 7,500 Total overhead cost $ 74,710 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 3,000 machine-hours rather than 3,100 machine-hours? Multiple Choice $72,650 $72,300 $73,300 $74,710
Martinez Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $362,000 and budgeted machine-hours were...
Martinez Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $362,000 and budgeted machine-hours were 24,000. Actual factory overhead was $393,000 and actual machine-hours were 27,000. Before disposition of under/overapplied overhead, the cost of goods sold was $610,000 and ending inventories were as follows:             Direct materials                    $ 80,000             WIP                                        200,000             Finished goods                       270,000                   Total                               $550,000 Required: a.   Determine the budgeted factory overhead rate per machine-hour. b.   Compute the over/underapplied overhead. c.   Prepare the journal entry to dispose of the variance using the write-off to cost of...
Schulz Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $266,400 and budgeted machine-hours were...
Schulz Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $266,400 and budgeted machine-hours were 18,500. Actual factory overhead was $287,920 and actual machine-hours were 19,050. Before disposition of under/overapplied overhead, the cost of goods sold was $560,000 and ending inventories were as follows: Direct Materials: $60,000 WIP: 190,000 Finished Goods: 250,000 Total: $500,000 1) Determine the budgeted factor overhead rate per machine-hour. 2) Compute the over/underapplied overhead. 3) Select the journal entry to dispose of the variance using...
Millner Corporation has provided the following data from its activity-based costing accounting system:Millner Corporation has provided...
Millner Corporation has provided the following data from its activity-based costing accounting system:Millner Corporation has provided the following data from its activity-based costing accounting system:        ACTIVITY COST POOLS          TOTAL COST                     TOTAL ACTIVITY DESIGNING PRODUCTS                $1,372,4478       7,798       PRODUCT DESIGN HOURS SETTING UP BATCHES                    33,300              740        BATCH SET UP ASSEMBLING PRODUCTS             126,160            6,640      ASSEBLY HOURS The activity rate for the "designing products" activity cost pool is closest to
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials...
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials $ 26,800 $ 22,800 Work in process $ 18,800 $ 11,800 Finished Goods $ 49,800 $ 57,800 Additional information: Raw materials purchases $ 73,800 Direct labor cost $ 93,800 Manufacturing overhead cost incurred $ 43,980 Indirect materials included in manufacturing overhead cost incurred $ 4,180 Manufacturing overhead cost applied to Work in Process $ 42,800 Any underapplied or overapplied manufacturing overhead is closed out...
PROBLEM. 1) Bledsoe Corporation has provided the following data for the month of November: Inventories: Beginning...
PROBLEM. 1) Bledsoe Corporation has provided the following data for the month of November: Inventories: Beginning Ending Raw materials $ 26,100 $ 22,100 Work in process $ 18,100 $ 11,100 Finished Goods $ 49,100 $ 57,100 Additional information: Raw materials purchases $ 73,100 Direct labor cost $ 93,100 Manufacturing overhead cost incurred $ 43,210 Indirect materials included in manufacturing overhead cost incurred $ 4,110 Manufacturing overhead cost applied to Work in Process $ 42,100 Any underapplied or overapplied manufacturing overhead...
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials...
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials $ 26,500 $ 22,500 Work in process $ 18,500 $ 11,500 Finished Goods $ 49,500 $ 57,500 Additional information: Raw materials purchases $ 73,500 Direct labor cost $ 93,500 Manufacturing overhead cost incurred $ 43,650 Indirect materials included in manufacturing overhead cost incurred $ 4,150 Manufacturing overhead cost applied to Work in Process $ 42,500 Any underapplied or overapplied manufacturing overhead is closed out...
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials...
Bledsoe Corporation has provided the following data for the month of November: Beginning Ending Raw materials $ 26,800 $ 22,800 Work in process $ 18,800 $ 11,800 Finished Goods $ 49,800 $ 57,800 Additional information: Raw materials purchases $ 73,800 Direct labor cost $ 93,800 Manufacturing overhead cost incurred $ 43,980 Indirect materials included in manufacturing overhead cost incurred $ 4,180 Manufacturing overhead cost applied to Work in Process $ 42,800 Any underapplied or overapplied manufacturing overhead is closed out...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT