In: Advanced Math
Soundex produces two models of satellite radios. Model A requires 15 minutes of work on Assembly Line I and 10 minutes of work on Assembly Line II. Model B requires 10 minutes of work on Assembly Line I and 12 minutes of work on Assembly Line II. At most 25 hours of assembly time on Line I and 22 hours of assembly time on Line II are available each day. Soundex anticipates a profit of $12 on Model A and $10 on Model B. Because of previous overproduction, management decides to limit the production of Model A satellite radios to no more than 80 per day.
Find the range of values that the resource associated with the time constraint on Assembly Line I can
assume.