Question

In: Economics

Using information from Question 5, determine the better option at interest rate 10% using Present Worth...

Using information from Question 5, determine the better option at interest rate 10% using Present Worth Analysis. Please solve using Excel if possible.

Question 5: Consider the following two alternatives that have no salvage value:

A

B

Initial Cost

Uniform Annual Benefits

Useful life, in years

$15,000

$3,000

8

$5,100

$1,800

4

Solutions

Expert Solution

Hi,

Hope you are doing well!

Question:

Answer:

Here, i will determine the better option through NPV method. Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time.

As per the qusetion:

For Project A:

Initial Cost = $15000

Uniform annual benefits = $3000

Useful Life = 8 years

Interest rate = 10%

NPV = Cash flow 0 + Cash flow1/(1+r)^1 + Cash flow2/(1+r)^2 + Cash flow3/(1+r)^3 + Cash flow4/(1+r)^4 + Cash flow5/(1+r)^5 + Cash flow6/(1+r)^6 + Cash flow7/(1+r)^7 + Cash flow8/(1+r)^8

= - $15000 + $3000/(1+10%)^1 + $3000/(1+10%)^2 + $3000/(1+10%)^3 + $3000/(1+10%)^4 + $3000/(1+10%)^5 + $3000/(1+10%)^6 + $3000/(1+10%)^7 + $3000/(1+10%)^8

= - $15000 + $3000/(1+ 0.1)^1 + $3000/(1+ 0.1)^2 + $3000/(1+ 0.1)^3 + $3000/(1+ 0.1)^4 + $3000/(1+ 0.1)^5 + $3000/(1+ 0.1)^6 + $3000/(1+ 0.1)^7 + $3000/(1+ 0.1)^8

=  - $15000 + $3000/(1.1)^1 + $3000/(1.1)^2 + $3000/(1.1)^3 + $3000/(1.1)^4 + $3000/(1.1)^5 + $3000/(1.1)^6 + $3000/(1.1)^7 + $3000/(1.1)^8

=  - $15000 + $3000/1.1 + $3000/1.21 + $3000/1.331 + $3000/1.4641+ $3000/1.61051 + $3000/1.771561 + $3000/1.9487171 + $3000/2.14358881

= - $15000 + 2727.27 + 2479.33 + 2253.94 + 2049.04 + 1862.76 + 1693.42 + 1539.47 + 1399.52

= - $15000 + $160004.75

NPV of project A = $10004.75

For Project A:

Initial Cost = $5100

Uniform annual benefits = $1800

Useful Life = 4 years

Interest rate = 10%

NPV = Cash flow 0 + Cash flow1/(1+r)^1 + Cash flow2/(1+r)^2 + Cash flow3/(1+r)^3 + Cash flow4/(1+r)^4

= - $5100 + $1800/1.1 + 1800/1.21 + $1800/1.331 + $1800/1.4641

= - $5100 + 1636.36 + 1487.60 + 1352.36 + 1229.42

= - $5100 + $5705.74 = $605.74

NPV of project B = $605.74

Here, NPV of project "A" is better than project "B" so, Project "A" is better than project "B" . So, Project "A" is  the better option.

Thank You


Related Solutions

Using information from Question 6, determine the better option at interest rate 15% using Present Worth...
Using information from Question 6, determine the better option at interest rate 15% using Present Worth Analysis. Please solve using Excel if possible. Question 6: A company is considering purchasing the following 4 different pieces of equipment of the same useful life of 5 years. The company can obtain a 15% annual return on its investment in other projects and is willing to invest money on one of the four pieces, as long as it can obtain 15% annual return...
Question 11 pts The interest rate at which the present worth and the equivalent uniform annual...
Question 11 pts The interest rate at which the present worth and the equivalent uniform annual worth are equal to 0 is called the internal rate of return. True False Question 21 pts To determine the internal rate of return, you can calculate net present worth at varying interests and select the interest rate where NPW = 0. True False Question 31 pts If the internal rate of return of a project is less than your MARR, then the project...
Using a Calculator and Present Value Table to Impute Interest Rate and Determine Present Value of...
Using a Calculator and Present Value Table to Impute Interest Rate and Determine Present Value of Operating Leases AutoZone reports the following in its 2015 Form 10-K. The Company leases some of its retail stores, distribution centers, facilities, land and equipment, including vehicles. Other than vehicle leases, most of the leases are operating leases... The Company has a fleet of vehicles used for delivery to its commercial customers and stores and travel for members of field management. The majority of...
Using the appropriate present value table and assuming a 12% annual interest rate, determine the present...
Using the appropriate present value table and assuming a 12% annual interest rate, determine the present value on December 31, 2018, of a five-period annual annuity of $6,200 under each of the following situations: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.) 1.The first payment is received on December 31, 2019, and interest is compounded annually. 2.The first payment is received on...
Using the appropriate present value table and assuming a 12% annual interest rate, determine the present...
Using the appropriate present value table and assuming a 12% annual interest rate, determine the present value on December 31, 2018, of a five-period annual annuity of $7,700 under each of the following situations: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.) 1.The first payment is received on December 31, 2019, and interest is compounded annually. 2.The first payment is received on...
Using the appropriate present value table and assuming a 12% annual interest rate, determine the present...
Using the appropriate present value table and assuming a 12% annual interest rate, determine the present value on December 31, 2018, of a five-period annual annuity of $5,600 under each of the following situations: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.) 1.The first payment is received on December 31, 2019, and interest is compounded annually. 2.The first payment is received on...
Calculate the future worth of the purchase shown below using an interest rate of 5% per...
Calculate the future worth of the purchase shown below using an interest rate of 5% per year. First Cost: -$21,000 Operating Cost: -$3,000/YR Salvage Value: $3,000 Useful Life: 3 Years
The IRR is the interest rate that makes the Present Worth "PW" of all the cash...
The IRR is the interest rate that makes the Present Worth "PW" of all the cash flows (inflows and outflows) equal to zero True False
Determine the breakeven (based on net present worth) initial cost for a project with an interest...
Determine the breakeven (based on net present worth) initial cost for a project with an interest rate of 6% and a useful life of 14 years with the following data: Annual Cost (O&M): $7,500/ year with an annual increase of $800/ year Annual Revenue = $9,000/ year with an annual increase of $1,000/ year Salvage Value: $50,000
Calculate and report and valid present worth measures using the listed interest for all the three...
Calculate and report and valid present worth measures using the listed interest for all the three options given below. What is the name of the best option economically? Dakota Delta Derby Interest 8% 8% 8% Purchase 127,000 79,000 102,000 Annual Revenue 44,800 48,600 94,400 Annual Expenses 44,800 48,600 94,400 Salvage 4,000 2,500 6,500 Life 6 6 6
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT