In: Accounting
Acquisition Cost of Long-Lived Assets
The following items represent expenditures (or receipts) related to the construction of a new home office for Lowrey Company.
Cost of land site, which included an old apartment building appraised at $75,000 | $166,000 |
Legal fees, including fee for title search | 2,200 |
Payment of apartment building mortgage and related interest due at time of sale | 9,400 |
Payment for delinquent property taxes assumed by the purchaser | 4,100 |
Cost of razing the apartment building | 18,000 |
Proceeds from sale of salvaged materials | (3,900) |
Grading to establish proper drainage flow on land site | 2,000 |
Architect's fees on new building | 310,000 |
Proceeds from sales of excess dirt (from basement excavation) to owner of adjoining property (dirt was used to fill in a low area on property) | (3,000) |
Payment to building contractor | 6,000,000 |
Payment of medical bills of employee accidentally injured while inspecting building construction | 2,400 |
Special assessment for paving city sidewalks (paid to city) | 19,000 |
Cost of paving driveway and parking lot | 26,000 |
Cost of installing lights in parking lot | 10,200 |
Premium for insurance on building during construction | 8,500 |
Cost of open house party to celebrate opening of new building | 9,000 |
Required
From the given data, calculate the proper balances for the Land, Building, and Land Improvements accounts of Lowrey Company.
Land | |
Building | |
Land Improvements |
SOLUTION
Land | Building | Land Improvements | |
Cost of land site, which included an old apartment building appraised at $75,000 | 166,000 | ||
Legal fees, including fee for title search | 2,200 | ||
Payment of apartment building mortgage and related interest due at time of sale | 9,400 | ||
Payment for delinquent property taxes assumed by the purchaser | 4,100 | ||
Cost of razing the apartment building | 18,000 | ||
Proceeds from sale of salvaged materials | (3,900) | ||
Grading to establish proper drainage flow on land site | 2,000 | ||
Architect's fees on new building | 310,000 | ||
Proceeds from sales of excess dirt (from basement excavation) to owner of adjoining property (dirt was used to fill in a low area on property) | (3,000) | ||
Payment to building contractor | 6,000,000 | ||
Special assessment for paving city sidewalks (paid to city) | 19,000 | ||
Cost of paving driveway and parking lot | 26,000 | ||
Cost of installing lights in parking lot | 10.200 | ||
Premium for insurance on building during construction | 8,500 | ||
Total | 216,800 | 6,315,500 | 36,200 |