Question

In: Finance

You are considering a project which requires $136,000 in external financing. The flotation cost of equity...

You are considering a project which requires $136,000 in external financing. The flotation cost of equity is 11 % and the cost of debt is 4.5 %. You wish to maintain a debt-equity ratio of.45. What is the initial cost of the project including the flotation costs?

Multiple Choice

  • $149,422

  • $143,367

  • $155,283

  • $138,009

  • $154,004

Solutions

Expert Solution

Calculation of weight
Debt 45% 45%/145% 31.03%
Equity 100% 100%/145% 68.97%
Total 145%
Calculation of Floatation cost
Project cost 136000
Assumed total floatation cost X
Total funding required (136000+X)
Source Weight Flotation cost Flotation cost Flotation cost Flotation cost
Debt (136000+X)*31.03% 4.50% (136000+X)*31.03%*4.5% (136000+X)*1.40% 1899.31+ 0.014 X
Equity (136000+X)*68.97% 11.00% (136000+X)*68.97%*11% (136000+X)*7.59% 10317.24+ 0.076 X
Total 12216.55+0.0898 X
Total floatation cost so computed is equal to the assumed total fixed cost of X
12216.55+0.0898 X= X
(1-0.0898) * X= 12216.55172
X= 12216.5517241379/0.910172413793103
X= $                    13,422
So total cost including flotation cost= 136000+13422
So total cost including flotation cost= $                  149,422
So option 1 is the right answer.

Related Solutions

ATT is considering a project. The project requires to purchase an equipment with a cost of...
ATT is considering a project. The project requires to purchase an equipment with a cost of $1.55 million. The equipment will be depreciated straight-line to a zero book value over the 9-year life of the project. At the end of the project it will be sold for a market value of $240,000. The project will not change sales but will reduce operating costs by $399,000 per year. The project also requires an initial investment of $52,000 in net working capital,...
xyz is evaluating the reno proejct. the project requires an intial investment of 136,000 that would...
xyz is evaluating the reno proejct. the project requires an intial investment of 136,000 that would be depreciated to 16,000 over 6 years using the straight-line depreciation. the projec is expected to have operating cash flows of 51,000 per year forever. xyz expects the project to have an after tax terminal value of 186,000 in 3 years. the tax rate is 30% what is (X+Y)/Z if the x is the projects relevant expected cash flow in 3 years, Y is...
Elemental is considering another project which requires new equipment at a cost of $70,000. The equipment...
Elemental is considering another project which requires new equipment at a cost of $70,000. The equipment has a 3 year tax life and will be fully depreciated by the straight-line method over 3 years. When the project closes down at the end of the third year, it is expected to sell for $5000 before taxes. The project will require new working capital of $10000, and is expected to be fully recovered at the end of the project's life. Project revenues...
Project A: This project requires an initial investment of $20,000,000 in equipment which will cost an...
Project A: This project requires an initial investment of $20,000,000 in equipment which will cost an additional $3,000,000 to install. The firm will use the attached MACRS depreciation schedule to expense this equipment. Once the equipment is installed, the company will need to increase raw goods inventory by $5,000,000, but it will also see an increase in accounts payable for $1,500,000. With this investment, the project will last 6 years at which time the market value for the equipment will...
You are considering investment in a project which will cost $50 million which will be depreciated...
You are considering investment in a project which will cost $50 million which will be depreciated to 0 over the next 3 years. The project will generate revenues of $13 million per year for the next 6 years with no expenses (other than depreciation). The company’s cost is capital is 8% and the corporate tax rate is 40%. After the 6 years, the project ends. What is the NPV of the project?
Compute the cost of debt financing. Compute the cost of equity financing using the capital asset...
Compute the cost of debt financing. Compute the cost of equity financing using the capital asset pricing model. Compute the weighted average cost of capital. The capital investment is to be depreciated as a 7 year asset using this table: Ownership year 1 (14.29%), year 2 (24.49%), year 3 (17.49%), year 4 (12.49%), year 5 (8.93%), year 6 (8.92%), year 7 (4.46%). Evaluate each independent project by computing net present value, internal rate of return, and payback. Then decide whether...
A project requires an initial investment or $9 million. the target D/E ratio is 0.60. Flotation...
A project requires an initial investment or $9 million. the target D/E ratio is 0.60. Flotation costs for equity are 7% and flotation costs for debt are 3%. whag is the true cost (in dollars) of the project when you consider the flotation costs?
You are considering a project which has a set up cost of $4,895, and which yields...
You are considering a project which has a set up cost of $4,895, and which yields $1,500, $2,000, and $2,500 at the end of the first, second, and third years after set-up. What is the internal rate of return on this project (Hint: trial and error) a. 5% b. 10% c. 15%
You are considering a project which has a set up cost of $4,895, and which yields...
You are considering a project which has a set up cost of $4,895, and which yields $1,500, $2,000, and $2,500 at the end of the first, second, and third years after set-up. What is the internal rate of return on this project? a. 5% b. 10% c. 15% d. None of these
COST OF COMMON EQUITY WITH AND WITHOUT FLOTATION The Evanec Company's next expected dividend, D1, is...
COST OF COMMON EQUITY WITH AND WITHOUT FLOTATION The Evanec Company's next expected dividend, D1, is $3.96; its growth rate is 4%; and its common stock now sells for $37. New stock (external equity) can be sold to net $31.45 per share. A. What is Evanec's cost of retained earnings, rs? Round your answer to two decimal places. Do not round your intermediate calculations. rs = % B. What is Evanec's percentage flotation cost, F? Round your answer to two...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT