In: Accounting
must state whether the Variance is Favourable or Unfavourable. To receive full credit your answer must be labeled as such. For example: An answer such as “- $4500” will not be given full credit, even if the number is correct. The same number shown as “$4500 Favourable” would receive full marks. The following are independent questions: 1. Information on Fleming Company's direct material costs follows: Actual amount of direct materials purchased and used 20,000 kilograms Actual direct material costs $40,000 Standard direct material costs $2.10 per kilogram Calculate the direct materials price variance – 2 marks 2. During March, Younger Company’s direct material costs for product T were as follows: Actual unit purchase price $6.50 per meter Standard quantity allowed for actual production 2,100 meters Quantity purchased and used for actual production 2,300 meters Standard unit price $6.25 per meter Calculate the materials usage variance – 2 marks 3. The following labour standards have been established for a particular product Standard labour hours per unit of output 1.7 hours Standard labour rate $14.25 per hour The following data pertains to operations concerning the product for the last month: Actual hours worked 3,700 hours Actual total labour cost $50,690 Actual output 2,300 units Calculate the labour rate variance – 2 marks 4. Yola Company manufactures a product with standards for direct labour of 4 direct labour-hours per unit at a cost of $12.00 per direct labour-hour. During June, 1,000 units were produced using 4,100 hours at $12.20 per hour. What was the direct labour efficiency variance? Calculate the labour efficiency variance – 2 marks
1.Actual Material 20000kgs
Actual material total cost = 40000$
standard cost $2.10 per kgs
direct materials price variance is difference between total actual cost and standard cost for actual quantity use.
= [Actual rate* Actual Quantity] - [Standard rate * actual quantity]
= [ $40000 ] - [$2.10 * 20000Kgs]
= $40000-$42000
=2000$
As the actual total cost are less than standard cost the proce variance is FAVORABLE
ANSWER : $2000 FAVORABLE
2.ACTUAL PRICE = $6.50
standard quantity = 2100
Actual quantity = 2300
Standard price = $6.25
materials usage variance = [Standard Rate * Actual Quantity ] - [Standard rate * standard quantity]
[$6.25*2300] - [$6.25*2100]
=$14375-$13125
=$1250 UNFAVORABLE [ACTUAL USAGE IS MORE THAN STANDARD ALLOWED]
3.STANDARD HOURS = 1.7
standard rate 14.25$
Actual hours =3700
Actual labor cost =50690$
units =2300
labour rate variance =[ Actual Rate * Actual Hours] - [ Standard Rate * Actual Hours]
=[50690$] - [$14.25*3700]
=50690$ - 52725$
=$2035 Favorable
4. direct labour efficiency variance = [Actual Hour*Standard rate] - [Standard hour* standard rate]
=[4100hours *$12] - [(4hours*1000units)*$12]
49200$-$48000
=$1200 UNFAVORABLE [ the actual hours are more than standard hours allowed]