Question

In: Statistics and Probability

A contractor is interested in the total cost of a project for which he intends to...

A contractor is interested in the total cost of a project for which he intends to bid. He estimates that materials will cost P25000 and that his labour will cost P900 per day. The contractor then formulates the probability distribution for completion time (X), in days, as given in the following table. Completion time in days (X) 10 11 12 13 14 P(X=x) 0.1 0.3 0.3 0.2 0.1 a) Determine the total cost function C for the project. b) Find the mean and variance for completion time X. c) Find the mean, variance and standard deviation for the total cost C.

Solutions

Expert Solution

Solution :

a) The total cost function is given as follows :

C = 25000 + 900.X

Where, C is total cost and X is completion time in number of days.

b) The mean of the completion time is given as follows :

The variance of the completion time is given as follows :

We have, E(X) = 11.9

Now,

c) If X is a random variable and C = a + bX, where a and b are two constants then,

E(C) = a + bE(X)

Var(C) = b² Var(X)

We have, C = 25000 + 900X, E(X) = 11.9 and Var(X) = 1.29

Hence,

E(C) = 25000 + (900 × 11.9) = 35710

The mean of the total cost is P35710.

Var(C) = (900)² × 1.29

Var(C) = 1044900

The standard deviation of the total cost is P1022.20.


Related Solutions

Question 1 A contractor is interested in the total cost of a project for which he...
Question 1 A contractor is interested in the total cost of a project for which he intends to bid. He estimates that materials will cost P25000 and that his labour will cost P900 per day. The contractor then formulates the probability distribution for completion time (X), in days, as given in the following table. Completion time in days (X) 10 11 12 13 14 P(X=x) 0.1 0.3 0.3 0.2 0.1 a) Determine the total cost function C for the project....
Medico Limited intends investing in a project during March 2021. The project is expected to cost...
Medico Limited intends investing in a project during March 2021. The project is expected to cost R2 500 000 with a five-year useful life, and no residual value. The annual volume of production for the project is estimated at 150 000 units, which can be sold for cash at R12 per unit. Depreciation is expected to be R500 000 per year. Annual cash operating costs are as follows: Variable costs R 225 000 Fixed costs. R 750 000 Rate of...
Medico Limited intends investing in a project during March 2021. The project is expected to cost...
Medico Limited intends investing in a project during March 2021. The project is expected to cost R2 500 000 with a five-year useful life, and no residual value. The annual volume of production for the project is estimated at 150 000 units, which can be sold for cash at R12 per unit. Depreciation is expected to be R500 000 per year. Annual cash operating costs are as follows: Variable costs R225 000 Fixed costs R750 000 The cost of capital...
Compute the average hourly cost to a contractor of a boilermaker involved on a project. The...
Compute the average hourly cost to a contractor of a boilermaker involved on a project. The boilermaker works on the second shift of a three-shift job and works six 10-hour days per week. Under the shift pay agreement, the boilermaker works 7 hours and is paid for 8 hours. Additional PL and PD insurance for $50,000/$100,000 coverage is required. Use 6.2% for FICA and 5.0% for unemployment insurance.
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursed construction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursedconstruction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of financial...
As an investment which he intends to keep for 10 years, a man bought a lot for P15,000 cash
ENGINEERING ECONOMYAs an investment which he intends to keep for 10 years, a man bought a lot for P15,000 cash. He wants a 12% after tax rate of return over and above the 8% inflation rate. If capital gains tax is 16% of his profit upon selling the lot, at what price must he sell the lot at the end of 10 years.
A capital budgeting replacement project has total installed cost of $100,000 which includes both an additional...
A capital budgeting replacement project has total installed cost of $100,000 which includes both an additional working capital investment of $15,000 and an after-tax salvage from the old asset of $3,000. The new project is expected to generate annual incremental cash flows after tax of $15,000 for the next 10 years with an expected terminal value at the end of the project of $18,000. The cost of capital of the project is 13% and the firm’s marginal tax rate is...
Maria Corporation Limited (MCL) is interested to invest in a project. The initial cost of the...
Maria Corporation Limited (MCL) is interested to invest in a project. The initial cost of the project is Rs. 11.5 million with the salvage value of Rs. 2 million. The project will generate generates revenue of Rs 15 million per year with variable cost of Rs. 6 million and other expenses of Rs. 4 million. The revenue and cost/expense will expected to increase by 5% per annum for first 3 years and 7.5% for last 2 years. MCL’s cost of...
Edward Foster is a building contractor. He and his customer have agreed that he will submit...
Edward Foster is a building contractor. He and his customer have agreed that he will submit a bill to them when he is 25 percent complete, 50 percent complete, 75 percent complete, and 100 percent complete. For example, he has a $200,000 room addition. When he has completed 25 percent, he will bill his customer $50,000. The problem occurs when he is 40 percent complete, has incurred expenses but cannot yet bill his customer. How can his revenue and expenses...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT