In: Accounting
Toyo Japan plant manufactures three product lines, all
multi-purpose kitchenware. The plant’s three product models are the
Product 1 (P1), the Product 2(P2), and the Product 3 (P3). Until
recently, the plant used a job-order product-costing system, with
manufacturing overhead applied on the basis of direct-labor hours.
The following table displays the basic data upon which the
traditional costing system was based.
Planned annual production
P1
P2
P3
Volume in units
5,000
4,000
1,000
Production runs
40 runs of 125 units
40 runs of 100 units
20 runs of 50 units
Direct Material
$129
$151
$203
Direct labor (not including setup)
9 hours @ $19 per hour
11 hours @ $19 per hour
13 hours @ $19 per hour
Machine Hours (MH) per product unit
10 machine hours
12 machine hours
17 machine hours
Total machine hours consumed by product line in a year
The annual budgeted overhead is $1,224,000, and the
company’s predetermined overhead rate is
$12 per direct-labor hour. The product costs for the three product
models, as reported under the plant’s traditional costing system,
are shown in the following table.
P1
P2
P3
Direct material
$129
$151
$203
Direct labor
9 hours @ 19 per hour
11 hours @ $19 per hour
13 hours @ $19 per hour
Manufacturing overhead
9 hours @ 12 per hour
9 hours @ 12 per hour
9 hours @ 12 per hour
Total
Toyo Japan’s pricing policy is to set a target price
for each product equal to 130 percent of the full product cost. Due
to price competition from other appliance manufacturers, P1 units
were selling at $525, and P2 units were selling for $628. These
prices were somewhat below the firm’s target prices. However, these
results were partially offset by greater-than-expected profits on
the P3 product line. Management had raised the price on the P3
model to $800, which was higher than the original target price.
Even at this price, Kitchen King’s customers did not seem to
hesitate to place orders, Moreover, the company’s competitiors did
not mount a challenge in the market for the P3 product line.
Neverthless, concern continued to mount in Toledo about the
difficulty in the P1 and P2 markets. After all, these were the
plant’s breadand-butter products, with projected annual sales of
5,000 P1 units and 4,000 P2 units.
Toyo Japan’s director of cost management, Angela Ramirez, had been
thinking for some time about a refinement in the Toledo plant’s
product-costing system. Ramirez wondered if the traditional,
volume-based system was providing management with accurate data
about product costs. She had read about activity-based costing, and
wondered if ABC would be an improvement to the plant’s
productcosting system. After some discussion, an ABC proposal was
made to the company’s top management, and approval was obtained.
The data collected for the new ABC system is displayed in the
following table.
Activity
Activity Cost Pool
Cost Driver
Product Line
Cost Driver quantity for product line
Machine Related
$310,500
Machine hours
P1
50,000
P2
48,000
P3
17,000
Total
Material handling
52,500
Production runs
P1
40
P2
40
P3
20
Total
Complete an activity-based costing analysis for Toyo
Japan’s three product lines regarding machine related, and material
handling activities.
Activity-based-costing analysis:
Activity |
Activity Cost Pool |
Cost Driver |
Cost Driver Quantity |
Pool Rate |
Product Line |
Cost Driver Quantity for Product Line |
Activity Cost for Product Line |
Product Line Prod. Volume |
Activity Cost per Unit of Product |
Machine |
$310,500 |
Machine |
115,000 |
$ 2.70 |
P1 |
50,000 |
$135,000 |
5,000 |
$27.00 |
Related |
Hours |
P2 |
48,000 |
129,600 |
4,000 |
32.40 |
|||
P3 |
17,000 |
45,900 |
1,000 |
45.90 |
|||||
Total |
115,000 |
$310,500 |
|||||||
Material |
52,500 |
Prod. |
100 |
525.00 |
P1 |
40 |
$ 21,000 |
5,000 |
4.20 |
Hand. |
Runs |
P2 |
40 |
21,000 |
4,000 |
5.25 |
|||
P3 |
20 |
10,500 |
1,000 |
10.50 |
|||||
Total |
100 |
$ 52,500 |
|||||||
Purch. |
75,000 |
Purch. |
300 |
250.00 |
P1 |
100 |
$ 25,000 |
5,000 |
5.00 |
Orders |
P2 |
96 |
24,000 |
4,000 |
6.00 |
||||
P3 |
104 |
26,000 |
1,000 |
26.00 |
|||||
Total |
300 |
$ 75,000 |
|||||||
Setup |
85,000 |
Prod. |
100 |
850.00 |
P1 |
40 |
$ 34,000 |
5,000 |
6.80 |
Runs |
P2 |
40 |
34,000 |
4,000 |
8.50 |
||||
P3 |
20 |
17,000 |
1,000 |
17.00 |
|||||
Total |
100 |
$ 85,000 |
|||||||
Inspect. |
27,500 |
Inspect. |
1,100 |
25.00 |
P1 |
400 |
$ 10,000 |
5,000 |
2.00 |
Hours |
P2 |
400 |
10,000 |
4,000 |
2.50 |
||||
P3 |
300 |
7,500 |
1,000 |
7.50 |
|||||
Total |
1,100 |
$ 27,500 |
|||||||
Ship. |
66,000 |
Ship. |
1,100 |
60.00 |
P1 |
500 |
$ 30,000 |
5,000 |
6.00 |
P2 |
400 |
24,000 |
4,000 |
6.00 |
|||||
P3 |
200 |
12,000 |
1,000 |
12.00 |
|||||
Total |
1,100 |
$ 66,000 |
|||||||
Eng. |
32,500 |
Eng. |
650 |
50.00 |
P1 |
250 |
$ 12,500 |
5,000 |
2.50 |
Hours |
P2 |
200 |
10,000 |
4,000 |
2.50 |
||||
P3 |
200 |
10,000 |
1,000 |
10.00 |
|||||
Total |
650 |
$ 32,500 |
|||||||
Fac. |
575,000 |
Machine |
115,000 |
5.00 |
P1 |
50,000 |
$250,000 |
5,000 |
50.00 |
Hours |
P2 |
48,000 |
240,000 |
4,000 |
60.00 |
||||
P3 |
17,000 |
85,000 |
1,000 |
85.00 |
|||||
Total |
115,000 |
$575,000 |
|||||||
Grand Total |
$1,224,000 |
Grand Total |
$1,224,000 |