Question

In: Operations Management

The distribution system for the Herman Company consists of three plants, two warehouses, and four customers....

The distribution system for the Herman Company consists of three plants, two warehouses, and four customers. Plant capacities and shipping costs per unit (in $) from each plant to each warehouse are as follows:

                       Warehouse

Plant           1                       2            Capacity

1                4                        7               450

2                8                         5              600

3                5                         6               380

                            Customer

Warehouse          1                        2                            3                             4

1                            6                       4                            8                             4

2                           3                         6                            7                             7

Demand                300                     300                         300                        400

Formulate the linear programming model to minimize the cost of shipping for this transshipment problem.

A-at the optimal solution how much is shipped from Plant 3 to Warehouse 1?

B-what is the range of optimality of coefficient of cost from Plant 3 to Warehouse 1 and what does this

mean?

C-what is the range of feasibility for the supply amount for Plant 2 and what does it mean?

D-what is the range of feasibility for the demand amount for customer 2 and what does it mean?

Solutions

Expert Solution

Let the units shipped from Plant 1 to Warehouse 1 be Xpw11, Plant 1 to Warehouse 2 be Xpw12 and so on. Hence, we get decision variables as Xpw11, Xpw12, Xpw21, Xpw22, Xpw31, Xpw32, Xwc11, Xwc12, Xwc13, Xwc14, Xwc21, Xwc22, Xwc23, Xwc24

Total cost = 4*Xpw11 + 7*Xpw12 + 8*Xpw21 + 5*Xpw22 + 5*Xpw31 + 6*Xpw32 + 6*Xwc11 + 4*Xwc12 + 8*Xwc13 + 4*Xwc14 + 3*Xwc21 + 6*Xwc22 + 7*Xwc23 + 7*Xwc24

We have to minimize this cost

Total Capacity = 450 + 600 + 380 = 1430

Total Demand = 300 + 300 + 300 + 400 = 1300

Total Demand < Total capacity. hence, we will get <= constraint for capacity

We get capacity constraints as:

Xpw11 + Xpw12 <= 450

Xpw21 + Xpw22 <= 600

Xpw31 + Xpw32 <= 380

We get Demand Constraints as:

Xwc11 + Xwc21 <= 300

Xwc12 + Xwc22 <= 300

Xwc13 + Xwc23 <= 300

Xwc14 + Xwc24 <= 400

We solve the given probelm in Excel using Excel solver as shown below. We further generate Sensitivity Reprot to anwer questions B to D.

The above table in the form of formulas along with Excel solver extract is shown below for better understanding and reference:

As seen from above, the units shipped from Plant 3 to warehouse 1 = 250 units

We solve further questions based on the sensitivity report shown below:

b. Under table for Variable cells,

Plant 3 to warehouse 1 conditions are given against Cell B5

Against Cell B5, the allowable increase for plant 3 to warehouse 1 = 0

Allowable decrease for plant 3 to warehouse 1 = 1

Hence, Range = 5 + 0 = 5 to 5 - 1 = 4

Hence, the range of optimality of coefficient of cost from Plant 3 to Warehouse 1 is 4 to 5. This means that out of this range if there is a change in the cost per unit of shipping, the optimal solution will change.

c. Under the table for constraints,

Plant 2 supply conditions are given against Cell D4.

Against Cell D4, the allowable increase for plant 2 supply = 0

Allowable decrease for plant 2 supply  = 130

Hence, range of feasibility = 600 + 0 = 600, 600 - 130 = 470.

If the capacity of Plant 2 changes out of this range, the optimal solution is changed.

d. Under the table for constraints,

Customer 2 demand conditions are given against Cell M11.

Against Cell M11, the allowable increase for Customer 2 demand = 130

Allowable decrease for Customer 2 demand  = 250

Hence, range of feasibility = 300 + 130 = 430, 300 - 250 = 50.

If the Demand for Customer 2 changes out of this range i.e more than 430 or less than 50, the optimal solution is changed.

_______________________________________________________________________________________

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

*Please include Spreadsheets and formulas, if applicable* The distribution system for the Herman Company consists of...
*Please include Spreadsheets and formulas, if applicable* The distribution system for the Herman Company consists of three plants, two warehouses, and four customers. Plant capacities and shipping costs per unit (in $) from each plant to each warehouse are as follows Warehouse Plant 1 2 Plant Capacity A 5 7 470 B 8 5 610 C 5 6 400 Customer demand and shipping costs per unit (in $) from each warehouse to each customer are as follows: Customer Warehouse Nikki...
A company needs to open new warehouses to distribute products to the customers in two different...
A company needs to open new warehouses to distribute products to the customers in two different regions. The company has to decide where to open warehouses and in which capacity should be preferred for them. Past data shows that average daily demand of customers are 1000 units for the customers in region 1 and 1200 units for the customers in region 2. There are two possible locations to open a warehouse. The daily equivalent setup cost of opening a warehouse...
A company has two warehouses A and B, and three retail outlets 1, 2 and 3....
A company has two warehouses A and B, and three retail outlets 1, 2 and 3. The warehouse capacities, retail outlet demands, and per-unit shipping costs ($) are shown in the table below. Formulate a linear programming (LP) model of this transportation problem with the objective of minimizing total shipping cost.                    Retail Outlets Warehouses    1       2     3 Total Supply      A    $5 $8 $3 500     B $7 $4 $6 250             Total Demand 300 400...
A system consists of three machines and two repairmen. At most two machines can operate at...
A system consists of three machines and two repairmen. At most two machines can operate at any time. The amount of time that an operating machine works before breaking down is exponentially distributed with mean 5 hours. The amount of time that it takes a single repairman to x a machine is exponentially distributed with mean 4 hours. Only one repairman can work on a failed machine at any given time. Let X(t) be the number of machines in working...
‏ You assume that a power system consists of four generators and seven loads . The...
‏ You assume that a power system consists of four generators and seven loads . The number of buses is thirteen . Each bus is connected to two buses in the system . Calculate the number of nonzeros in the Jacobian matrix and the number of nonzeros in the bus admittance matrix for this system . Why is a slack bus needed in the power flow analysis ?
At a certain company, any valid password consists of four digits followed by two lower case...
At a certain company, any valid password consists of four digits followed by two lower case letters. Determine how many passwords are possible if the first digit cannot be a 0, the last letter must be a vowel (a, e, i, o, u) and repetition of any letter or any digit is not permitted?
WestFuel produces a special fuel system component at its three plants. The company currently has orders...
WestFuel produces a special fuel system component at its three plants. The company currently has orders from four customers. After considering relevant costs, WestFuel can expect the following per-unit profit for each plant–customer alternative. Customer 1 Customer 2 Customer 3 Customer 4 Plant 1 $15 $17 $18 $20 Plant 2 $17 $14 $19 $16 Plant 3 $18 $17 $17 $19 The manufacturing capacities during the current production period are: Plant 1, 5,000 units; Plant 2, 3,500 units; Plant 3, 4,000...
LM.72 A potato processing company has four plants in Southeast Idaho and sources potatoes from three...
LM.72 A potato processing company has four plants in Southeast Idaho and sources potatoes from three different farms. You need to help them develop a sourcing plan which minimizes transportation costs. The tables below show (1) how many tons of potatoes can be supplied be each farm, (2) the monthly demand for each plant, and (3) the cost per ton of shipping from each farm to each plant. Plant 1 Plant 2 Plant 3 Plant 4 50 70 50 30...
Company ABC is considering opening warehouses in four cities in Canada: Ottawa, Toronto, Calgary and Winnipeg....
Company ABC is considering opening warehouses in four cities in Canada: Ottawa, Toronto, Calgary and Winnipeg. Each warehouse can ship 100 units per day. The daily fixed cost of keeping each warehouse open is $400 for Ottawa, $500 for Toronto, $300 for Calgary and $350 for Winnipeg. Region 1 of the country requires 80 units per day, region 2 requires 70 units per day and region 3 requires 40 per day. The costs (including production and shipping costs) of sending...
Frandec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers. One...
Frandec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers. One product, called a Liftmaster, is assembled from four components: a frame, a motor, two supports, and a metal strap. Frandec’s production schedule calls for 4000 Liftmasters to be made next month. Frandec purchases the motors from an outside supplier, but the frames, supports, and straps may be either manufactured by the company or purchased from an outside supplier. Manufacturing and purchase costs per unit...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT