Question

In: Finance

Assume a project will produce cash flows of $12,079, $20,823, $36,524 at the end of Years...

Assume a project will produce cash flows of $12,079, $20,823, $36,524 at the end of Years 1 to 3, respectively. If the discount rate is 12 percent, what is the current value of these cash flows?

Solutions

Expert Solution

Present value=Cash flows*Present value of discounting factor(rate%,time period)

=12079/1.12+20823/1.12^2+36524/1.12^3

which is equal to

=$53381.85(Approx)


Related Solutions

22. A project will not produce any cash flows for two years. Starting in the third...
22. A project will not produce any cash flows for two years. Starting in the third year, it will produce annual cash flows of $11,900 a year for two years. The project initially costs $43,600. In Year 6, the project will be closed and as a result should produce a final cash inflow of $50,500. What is the net present value of this project if the required rate of return is 8.7 percent? $5,474.76 $3,935.56 $5,447.76 $7,465.95 $4,802.57
An investment is expected to produce cash flows of $1,000 at the end of each of...
An investment is expected to produce cash flows of $1,000 at the end of each of the next 6 years, then an additional lump sum payment of $1,500 at the end of Year 6. What is the maximum price you are willing to pay for this investment now if your expected rate of return is 4%? Select one: a. $5,324.89 b. $5,974.77 c. $5,568.13 d. $6,427.61 e. $4,854.13
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
Aerospace Dynamics will invest $180,000 in a project that will produce the following cash flows. The...
Aerospace Dynamics will invest $180,000 in a project that will produce the following cash flows. The cost of capital is 11 percent. (Note that the fourth year’s cash flow is negative.) Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods. Year Cash Flow 1. $ 62,000 2. 74,000 3. 66,000 4. (63,000 ) 5. 140,000 a. What is the net present value of the project? (Negative amount should be indicated...
Aerospace Dynamics will invest $150,000 in a project that will produce the following cash flows. The...
Aerospace Dynamics will invest $150,000 in a project that will produce the following cash flows. The cost of capital is 10 percent. (Note that the fourth year’s cash flow is negative.) Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods.    Year Cash Flow 1 $ 45,000 2 57,000 3 65,000 4 (48,000 ) 5 140,000 a. What is the net present value of the project?
You are evaluating a project that will cost $497,000​, but is expected to produce cash flows...
You are evaluating a project that will cost $497,000​, but is expected to produce cash flows of $123,000 per year for 10 ​years, with the first cash flow in one year. Your cost of capital is 11.2% and your​ company's preferred payback period is three years or less. a. What is the payback period of this​ project? b. Should you take the project if you want to increase the value of the​ company? a. What is the payback period of...
Waste Industries is evaluating a $55,500 project with the following cash flows. Years Cash Flows 1...
Waste Industries is evaluating a $55,500 project with the following cash flows. Years Cash Flows 1 $ 9,120 2 20,200 3 26,600 4 16,300 5 26,300 The coefficient of variation for the project is 0.475. Coefficient of Variation Discount Rate 0 − 0.25 7 % 0.26 − 0.50 9 % 0.51 − 0.75 13 % 0.76 − 1.00 16 % 1.01 − 1.25 19 % Use Appendix B for an approximate answer but calculate your final answer using the formula...
A project will produce cash inflows of $1,750 a year for four years. The project initially...
A project will produce cash inflows of $1,750 a year for four years. The project initially costs $10,600 to get started. In year five, the project will be closed and as a result should produce a cash inflow of $8,500. What is the net present value of this project if the required rate of return is 14.75%?   -$1,306.18 -$935.56   $5,474.76   $1,011.40
8. Project R has a cost of $ 10,000 and in expected to produce cash flows...
8. Project R has a cost of $ 10,000 and in expected to produce cash flows per year of $ 4,000 for 3 years. Project S has a cost of $20,000 and in expected to produce cash flows of $ 7,000 per year for 4 years. Calculate the 2 projects' NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 11%. Which project should be selected ?
You are evaluating a project that is expected to produce cash flows of $5,000 each year...
You are evaluating a project that is expected to produce cash flows of $5,000 each year for the next 3 years and $7,000 each year for the following 3 years. The IRR of this 6-year project is 12%. If the firm’s WACC is 10%, what is the project’s NPV?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT