In: Accounting
Oakwood Company produces maple bookcases to customer order. The
following information is available for the production of the
bookcases.
Process time |
9.0 days |
Inspection time |
1.5 days |
Move time |
3.7 days |
Wait time |
14.0 days |
Required:
1. Compute the company’s manufacturing cycle
time.
2. Compute the company’s manufacturing cycle
efficiency.
3. Management believes it can reduce move time by
1.10 days and wait time by 2.50 days by adopting lean manufacturing
techniques. Compute the company’s manufacturing cycle efficiency
assuming the company’s predictions are correct.
Complete this question by entering your answers in the tabs below.
Required 1
Compute the company’s manufacturing cycle time. (Round your answers to 1 decimal place.)
|
Complete this question by entering your answers in the tabs below.
Required 2
|
d Complete this question by entering your answers in the tabs below.
Required 3
Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company’s manufacturing cycle efficiency assuming the company’s predictions are correct. (Round your answers to 1 decimal place.)
|
Note: Please solve the problem completely. Thank you
Solution:
Throughput Time / Manufacturing Cycle Time
Throughput time is the amount of time required for a product to pass through a manufacturing process, thereby being converted from raw materials into finished goods. Throughput time includes following times:
- Processing time --- it is the time taken to process/make the product (Conversion time from raw material to finished goods)
- Inspection Time – Time taken for inspecting the raw material, WIP and finished product.
- Move time – time required to move products into and outside of the manufacturing unit.
- Queue time – time spent waiting prior to the processing, inspection and move activities.
Throughput Time = Process time + Inspection time + Move time + Queue time
Manufacturing Cycle Efficiency
It measures the proportion of production time spent on value added activities.
The process time in the throughput time calculation is considered value added time, since this is the only step that actually produces the product.
The rest time is administrative and logistical non value added time.
Manufacturing Cycle Efficiency = Total Value Added Time / Total Throughput Time x 100
Part 1 –
Manufacturing Cycle Time |
||
Time |
||
Process time |
9 |
days |
Inspection time |
1.5 |
days |
Move time |
3.7 |
days |
Wait time |
14 |
days |
Manufacturing cycle time |
28.2 |
days |
Part 2 –
Manufacturing Cycle Efficiency |
||||
Choose Numerator: |
/ |
Choose Denominator: |
= |
Manufacturing cycle efficiency |
Total Value added time |
/ |
Total manufacturing cycle time or total throughput time |
= |
Manufacturing cycle efficiency |
9 |
/ |
28.2 |
= |
0.3191 or 31.91% |
Part 3 –
Total Revised Manufacturing Cycle Time =
Manufacturing Cycle Time |
||
Time |
||
Process time |
9 |
days |
Inspection time |
1.5 |
days |
Move time (3.7 – 1.1) |
2.6 |
days |
Wait time (14 – 2.5) |
11.5 |
days |
Manufacturing cycle time |
24.6 |
days |
Manufacturing Cycle Efficiency |
||||
Choose Numerator: |
/ |
Choose Denominator: |
= |
Manufacturing cycle efficiency |
Total Value added time |
/ |
Total manufacturing cycle time or total throughput time |
= |
Manufacturing cycle efficiency |
9 |
/ |
24.6 |
= |
0.3659 or 36.59% |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you