In: Finance
Prepare an Excel spreadsheet to present your financial decisions for two projects using NPV, IRR and the Payback Period techniques.
There are two mutually exclusive projects A and B. Both projects require an investment of $10 million but the timing is different for the rest of the expected net cash flows.
For project A For project B
Period 0 = - $10.0 m - $10.0 million
Period 1 = 6.5 3.5 m
Period 2 3.0 3.5
Period 3 = 3.0 3.5
Period 4 = 1.5 3.5
Total Inflow = $14.0m $14.0m
Prepare 3 possible scenarios for each project. Use the 5% discount rate (WACC) for a forecast if these are low risk projects, 10% if we think they have a normal amount of risk and 15% if we decide that these are high risk projects.
Formulas Used:-
Year | Project A | Project B | |
0 | -10000000 | -10000000 | |
1 | 6000000 | 3500000 | |
2 | 3000000 | 3500000 | |
3 | 3000000 | 3500000 | |
4 | 1500000 | 3500000 | |
Payback | =2+(-B2-SUM(B3:B4))/B5 | =2+(-C2-SUM(C3:C4))/C5 | |
IRR | =IRR(B2:B6) | =IRR(C2:C6) | |
Disc. Rate | 0.05 | 0.1 | 0.15 |
NPV A | =NPV(B11,$B$3:$B$6)+$B$2 | =NPV(C11,$B$3:$B$6)+$B$2 | =NPV(D11,$B$3:$B$6)+$B$2 |
NPV B | =NPV(B11,$C$3:$C$6)+$C$2 | =NPV(C11,$C$3:$C$6)+$C$2 | =NPV(D11,$C$3:$C$6)+$C$2 |
Decision Rule:-
Payback Period = Project A should be Choose because it has lower payback period
NPV= When Discount rate is 5% the project B should be choose. When Discount rate is 10% the project A should be choose and When Discount rate is 15% the project A should be choose.
IRR = at Any Discount Rate the project A should be choose because it has Higher IRR.