In: Accounting
“That old equipment for producing carburetors is worn out,” said Bill Seebach, president of Hondrich Company. “We need to make a decision quickly.” The company is trying to decide whether it should rent new equipment and continue to make its carburetors internally or whether it should discontinue production of its carburetors and purchase them from an outside supplier. The alternatives follow:
Alternative 1: Rent new
equipment for producing the carburetors for $176,000 per
year.
Alternative 2: Purchase
carburetors from an outside supplier for $20.70 each.
Hondrich Company’s costs per unit of
producing the carburetors internally (with the old equipment) are
given below. These costs are based on a current activity level of
32,000 units per year:
Direct materials | $ | 5.70 | |
Direct labour | 10.00 | ||
Variable overhead | 2.00 | ||
Fixed overhead ($2.75 supervision, $1.80
depreciation, and $4.00 general company overhead) |
8.55 | ||
Total cost per unit | $ | 26.25 | |
The new equipment would be more
efficient and, according to the manufacturer, would reduce direct
labour costs and variable overhead costs by 25%. Supervision cost
($88,000 per year) and direct materials cost per unit would not be
affected by the new equipment. The new equipment’s capacity would
be 50,000 carburetors per year.
The total general company overhead
would be unaffected by this decision.
Required:
1. Seebach is unsure what the company should do
and would like an analysis showing the unit costs and total costs
for each of the two alternatives given above. Assume that 32,000
carburetors are needed each year.
a. What will be the total relevant cost
of 32,000 subassemblies if they are manufactured internally as
compared to being purchased?
b. What would be the per unit cost of the each subassembly manufactured internally? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
c. Which course of action would you recommend to the president?
Indifferent between the two alternatives
Manufacture internally
Purchase from the outside supplier
2. Seebach is unsure what the company should do and would like an analysis showing the unit costs and total costs for each of the two alternatives given above.
a-1. What will be the total relevant cost
of 44,000 subassemblies if they are manufactured internally?
a-2. What would be the per unit cost of subassembly? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
a-3. Which course of action would you recommend if 44,000 assemblies are needed each year?
Purchase from the outside supplier
Manufacture internally
Indifferent between the two alternatives
b-1. What will be the total relevant cost of 50,000 subassemblies if they are manufactured internally?
b-2. What would be the per unit cost of subassembly? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
b-3. Which course of action would you recommend if 50,000 assemblies are needed each year?
Purchase from the outside supplier
Indifferent between the two alternatives
Manufacture internally
3. Not available in Connect.
After taking new machinery the cost will be | ||||
particular | old cost /unit $ | cost reduction | new cost / unit $ | |
A | B | a*(1-B) | ||
Direct material | 5.7 | 0 | 5.7 | |
Direct labour | 10 | 25% | 7.5 | |
Variable overhead | 2 | 25% | 1.5 | |
What will be the total relevant cost of 32,000 subassemblies if they are manufactured internally as compared to being purchased?
Particular | Cost | Amount $ | Amount $ |
Direct material | $5.7 | $ 182400 | |
Direct labour | $7.5 | $ 240000 | |
Variable overhead | $1.5 | $ 48000 | $470400 |
Add - fixed overhead | |||
Rent new equipment | $176000 | ||
Supervision ($2.75*32000) | $88000 | $264000 | |
Total cost | $734400 | ||
subassemblies Produce | 32000 | ||
cost per subassemblies $734400/32000 | $22.95 | ||
so manufacturing cost for per subassemblies are $22.95
Purchase cost from an outside supplier for $20.70 each.
so if co puchase from outside saving will be $2.25 per subassemblie , so co sgould go for purchase from outside option .
1- B )What would be the per unit cost of the each subassembly manufactured internally = $ 22.95 (above )
1 - C) Which course of action would you recommend to the president? - co. should go for purchase outside
2 ) cost for 44000 subassembliy
Particular | Cost | Amount $ | Amount $ |
Direct material | $5.7 | $ 250800 | |
Direct labour | $7.5 | $ 330000 | |
Variable overhead | $1.5 | $ 66000 | $ 646800 |
Add - fixed overhead | |||
Rent new equipment | $176000 | ||
Supervision | $88000 | $264000 | |
Total cost | $ 910800 | ||
subassemblies Produce | 44000 | ||
cost per subassemblies $910800/44000 | $20.70 | ||
so manufacturing cost for per subassemblies are $20.70
Purchase cost from an outside supplier for $20.70 each.
here in both option cost per subassembly is same so cand can go for purchase from outside or can manufacture
2 ) cost for 50000subassembliy
Particular | Cost | Amount $ | Amount $ |
Direct material | $5.7 | $ 285000 | |
Direct labour | $7.5 | $ 375000 | |
Variable overhead | $1.5 | $ 75000 | $ 735000 |
Add - fixed overhead | |||
Rent new equipment | $176000 | ||
Supervision | $88000 | $264000 | |
Total cost | $ 999000 | ||
subassemblies Produce | 50000 | ||
cost per subassemblies $999000 / 50000 | $19.98 | ||
so manufacturing cost for per subassemblies are $19.98
Purchase cost from an outside supplier for $20.70 each.
in this situation co should manufacture because if purchase from outside co . pay $0.72 more per subassembly as compare to manufacture