Question

In: Accounting

Hyde Park Elementary has plans to build a new playground in 2017. They received a $120,000...

Hyde Park Elementary has plans to build a new playground in 2017. They received a $120,000 government grant to be used for building the playground. They are hoping to break ground in May 2017 and complete the project by the start of school in September. Before they can start the project, however, they must dismantle the existing playground that has become unsafe based on current safety standards. They are also planning to complete soil testing once the existing playground is dismantled as a number of residential properties in the community have tested positive for soil contamination. Due to recent news articles, parents are very concerned about the potential for soil contamination and are demanding a full test to ensure their kids are not playing on a contaminated playground.

Sonya Muhammed, the school principal, has compiled the following estimates related to the new playground:

Cost for dismantling existing equipment

$22,000

Salvage value from the metal from existing equipment

$7,000

Soil testing

$18,000

New playground equipment

$45,000

Cost of installation

$16,000

Cost of resurfacing play area in rubber

$55,000

Cost of landscaping (including $5,000 for gravel)

$22,000

Cost of removing and replacing soil

$73,000

The costs for installation, resurfacing, landscaping, and soil removal are the costs quoted by professional contractors. Sonya was approached by the president of the student council, Josh Schwinn, who has volunteered the council’s time for installing and landscaping the new playground. This will save the school approximately $25,000 in costs and Sonya has decided to accept this offer as two of the council members who will be helping are journeymen carpenters.

The school has two options in terms of dealing with the contaminated soil. The first option is to not partake in the soil testing and to simply resurface the play area with a poured-rubber matting that can cover the entire play surface. This will cost, as Sonya indicated in her estimates above, approximately $55,000 – a large chunk of the playground budget. The other option is to perform the soil testing. A municipal worker has estimated that there is a 40% chance that the soil is contaminated. If this is the case, the school will either need to resurface the area for $55,000 or it can have the contaminated soil removed and replaced for a hefty cost of $73,000 plus the cost of gravel. However, there is a 60% chance that the soil will not be contaminated. Sonya is wondering what they should do and has asked for your help.

REQUIRED

Prepare an analysis of the potential project costs for the following scenarios. Note: There is no need for gravel in the resurfacing scenario.

  1. Resurface ground without doing soil testing .
  2. Complete the soil testing. In this case there are two outcomes:

  1. remove/replace the soil if contaminated.
  2. resurface if contaminated.

Use the probabilities provided by the municipal worker to determine a weighted cost for each of these outcomes.

  1. What option would you recommend for the school? Why? Are there other non-financial considerations that you need to include in your decision?

Solutions

Expert Solution


Related Solutions

Fun City has decided to build a new municipal water park with pools, water slides, and...
Fun City has decided to build a new municipal water park with pools, water slides, and so forth. You have been hired to conduct a study to determine if the water park can pass the test. A nearby and very similar city currently has a water park similar to the one Fun City is considering. The nearby city currently charges $10 for admission and, on a typical day, attracts 4,000 persons. Last year, it charged $15, but only attracted 3,000...
At the beginning of 2017, the Mini Construction Company received a contract to build an office...
At the beginning of 2017, the Mini Construction Company received a contract to build an office building for $1.2 million. Mini will construct the building according to specifications provided by the buyer, and the project is estimated to take four years to complete. The cost breakdown is as follows. Determine the amount of revenue and gross profit to be recognized each year. (do not include $ in your answer, round to 4 decimal places). 2017 2018 2019 2020 cost incurred...
Toledo Stadium The city of Toledo has received a proposal to build a new multipurpose outdoor...
Toledo Stadium The city of Toledo has received a proposal to build a new multipurpose outdoor sports stadium. The expected life of the stadium is 20 years. It will be financed by a 20-year bond paying 8 percent interest annually. The stadium's primary tenant will be the city's Triple-A baseball team, the Red Hots. The plan's backers anticipate that the site also will be used for rock concerts and college and high school sports. The city does not pay any...
The city of Miami has received a proposal to build a new multipurpose outdoor sports stadium....
The city of Miami has received a proposal to build a new multipurpose outdoor sports stadium. The expected life of the stadium is 20 years. It will be financed by a 20-year industrial development bond that will require a payment of 8 percent interest annually. The stadium’s primary tenant will be the city’s Triple-A baseball team, the Mudhawks. The plan’s backers anticipate that the new facility will also be used for rock concerts and college and high school sports events....
3. You are the CFO of a company looking to build a new office park beginning...
3. You are the CFO of a company looking to build a new office park beginning five years from now. You will need $2M to purchase land at that time and immediately hypothecate the parcel to stand for a 24-month, straight (non-amortizing) construction loan of $1.5M @ 7%. Also at that time you will pay a half point commitment fee to the take-out lender. Upon completion (seven years from now), the take-out lender will take over the construction loan balance...
A manufacturer plans to open a new plant. The new plant will cost $4,000,000 to build...
A manufacturer plans to open a new plant. The new plant will cost $4,000,000 to build and make ready for production. Company management believes that the plant will produce a net profit of $130,000 in the first year and that profit will increase 5% per year until year 7 at which point profit will remain constant for the remainder of the plant’s useful life. Determine the payback period for the plant. Do not consider the effect of interest. Express your...
A   production   company   plans   to   build   a   new   warehouse   in   order   to   supply   its   new &nb
A   production   company   plans   to   build   a   new   warehouse   in   order   to   supply   its   new   sales   points.   On   the   basis   of   a   preliminary   analysis   of   the   problem,   it   has   been   decided   that   the   facility   should   accommodate   at   least   800   pallets   of   80×80   cm2   dimension.   The   pallets   will   be   stored   onto   conventional   racks   and   transported   by   means   of   reach   trucks.   Each   rack   has   four   shelves,   each   of   which   can   store   a   single   pallet.   Each   pallet   occupies   a   1.0×1.0   m2   area.   Racks  ...
An unmarried taxpayer with AGI of $120,000 in 2017 has a tax liability of $21,000. The...
An unmarried taxpayer with AGI of $120,000 in 2017 has a tax liability of $21,000. The taxpayer's 2018 AGI and tax liability are $175,000 and $31,000, respectively. To avoid any penalty for underpayment of estimated tax in 2018, the minimum amount the taxpayer must prepay during 2018 is: A. $21,000 B. $23,100 (marked incorrect on test results already) C. $27,900 D. $31,000 E. $34,100
The Montgomery Biscuits recently announced plans to build a new $35,000,000 baseball stadium in Montgomery, Alabama....
The Montgomery Biscuits recently announced plans to build a new $35,000,000 baseball stadium in Montgomery, Alabama. The Biscuits play in the Southern League and are the Double-A farm club of the Tampa Bay Rays. The operating costs of the new 10,000 seat stadium are expected to average $300,000 per year for the first fifteen years, then they are expected to increase by $20,000 per year for the next ten years, after which they will remain constant throughout the life of...
Wilson and Sons Corp. has bought a prime parcel of beachfront property and plans to build...
Wilson and Sons Corp. has bought a prime parcel of beachfront property and plans to build a luxury hotel. After meeting with the architectural team, the Wilson family has drawn up some information to make preliminary plans for construction. Excluding the suites, which are not part of this decision, the hotel will have four kinds of rooms: beachfront non-smoking, beachfront smoking, lagoon view non-smoking, and lagoon view smoking. In order to decide how many of each of the four kinds...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT