As concrete cures, it gains strength. The following data represent the 7-day and 28-day strength in pounds per square inch (psi) of a certain type of concrete. Complete parts (a) through (f) below.
7-Day Strength (psi), x |
3380 |
3390 |
2300 |
2480 |
2620 |
|
---|---|---|---|---|---|---|
28-Day Strength (psi), y |
5020 |
5220 |
4070 |
4120 |
4190 |
(a) Treating the 7-day strength as the explantory variable, x , use technology to determine the estimates of β0 and β1.
β0 ≈b0 = ____ (Round to two decimal places as needed.)
β1 ≈b1 = ____ (Round to two decimal places as needed.)
(b) Compute the standard error of the estimate , se.
se= ______ ( Rounding to four decimal places)
(c) A normal probability plot suggests that the residuals are normally distributed . Use technology to determine sb1 .
Sb1= _____ ( Rounding to four decimal places)
(d) A normal probability plot suggests that the residuals are normally distributed. Test whether a linear relation exists between 7-day strength and 28-day strength at the α=0.05 level of significance.
The first step is to set up a hypothesis test. The parameter being tested is the slope, β1, of the linear regression line. If there is no linear relation between the response and explanatory variables, the slope of the true regression line will be zero.
The P-value for this test is _____ (rounding to three decimal places.)
(e) Use technology to construct a 95% confidence interval about the slope of the true least-squares regression line.
Lower bound: ____
Upper bound : _____
(f) What is the estimated mean 28-day strength of this concrete if the 7-day strength is 3000 psi?
Y= ______
a) bo=1553.566
b1=1.048
b)se=119.6316
c)sb1=0.1160
d)p value =0.003
e) Lower bound: 0.679
Upper bound =1.417
f)
y=1553.566+1.048*3000 =4697.57 (try 4697.99 if this comes wrong)