Exercise 6.8: The plant manager of manard Services has
received five projects from his managers.
He uses a
MARR of 9% to make project decisions. Find NPW, NFW, and EUAQ for
the projects.
Year
Project U
Project V
Project W
Project X
Project Y
0
($211,345)
($6,000)
($425,000)
($578,000)
($821,000)
1
$5,000
$1,500
$5,000
$85,000
$85,000
2
$8,800
$16,500
$13,800
$234,600
$85,000
3
$15,488
$18,150
$38,088
$647,496
$234,600
4
$27,259
$19,865
$44,182
$751,095
$272,136
5
$47,976
$21,862
$51,251
$871,271
$315,678...