In: Accounting
QUESTION 1 [41 MARKS]
ABC Holdings is considering two projects. The projects are similar
in nature and are expected to both operate for four years. Due to
unavailability of funds to undertake both of them, only one project
can be accepted. The cost of capital is 12%.
The following information is available:
Net cash flows | ||
Project A | Project B | |
N$000 | N$000 | |
Initial Investment | 46000 | 46000 |
Year 1 | 17000 | 15000 |
Year 2 | 14000 | 13000 |
Year 3 | 24000 | 15000 |
Year 4 | 9000 | 25000 |
Estimated scrap value at the end of year 4 | 4000 | 4000 |
Depreciation is charged on the straight line basis.
1. Assuming that the management of ABC holdings have decided to undertake both projects and the projects can be undertaken in part, how much NPV will they get if they have N$80 000 000 available to invest.
2. Explain three non-financial considerations that should be taken into account before a project is chosen
Step 1: Since, Organisation is having 2 projects and organisation can accept only one project due to lack of fund available, Organisation should accept that project, which result in higher NPV.
Net Cash Flows | |||||||
Project A | Project B | ||||||
Particulars | Year | N$000 | PVF@12% | PV of Cash Flow | N$000 | PVF@12% | PV of Cash Flow |
Initial O/F | 0 | 46000 | 1 | -46000 | 46000 | 1 | -46000 |
Inflow | 1 | 17000 | 0.892857 | 15178.57 | 15000 | 0.892857 | 13392.85714 |
Inflow | 2 | 14000 | 0.797194 | 11160.71 | 13000 | 0.797194 | 10363.52041 |
Inflow | 3 | 24000 | 0.71178 | 17082.73 | 15000 | 0.71178 | 10676.70372 |
Inflow | 4 | 9000 | 0.635518 | 5719.663 | 25000 | 0.635518 | 15887.95196 |
Scrap | 4 | 4000 | 0.635518 | 2542.072 | 4000 | 0.635518 | 2542.072314 |
NET PRESENT VALUE (NPV) OF A | 5683.747 | NPV 'B' | 6863.105542 |
Since, Project B is having NPV more than Project A, Organisation should go for Project B.
Step 2: ( Answer 1) Since, Organisation is undertaking both project, but due to insufficiency of fund, organisation should undertake Project B (in full) due to its high NPV ( at same amount of initial investment) and Project A ( in part)
So, NPV would be:
Project B NPV + Project A NPV in part
i.e. 6863.11+ 5683.75*(( 80000-46000)/46000)
i.e. 6863.11+4201.03
= 11064.1 Ans.
Step 3: Non Financial Considerations:
1. Feasibility Study: whether the feasibility study is carried out, and project is feasible in all respect including technical, economical, financial, legal etc.
2. Reputation/ Goodwill: whether the aforementioned projects would add on the reputation or morale in the mind of the investor and general public? sometimes +ve NPV projects are also not considered good and viable as they may result in negative goodwill to the organisation.
3. Ease of Maintenance: whether the project is able to be maintened by the organisation? if not, project should not be started.