Question

In: Economics

A light-rail transportation project is proposed to connect the centre of a city to a growing suburban neighbourhood.

 

A light-rail transportation project is proposed to connect the centre of a city to a growing suburban neighbourhood. The project is expected to cost $480 million for construction, right-of-way purchase, and traffic control systems. Half the cost must be allocated at the beginning of the project and the other half is paid upon construction completion. Construction is expected to take two years. The useful life of this project is 20 years after construction is completed. Operation and maintenance cost is expected to be $13 million per year after construction is completed. The project is expected to generate ridership revenues of $38 million per year (after construction).

This new transportation alternative is expected to generate a total of $26 million per year in benefits in terms of travel time savings and safety improvements. Because this is a public project, the ridership revenues in terms of tickets are to be treated as negative costs not benefits, i.e., there is no direct benefit to the society by charging consumers. The social discount rate for this project is chosen to be 3%.

Calculate the benefit/cost ratio of this project and comment on its feasibility.

Solutions

Expert Solution


Related Solutions

The City of G is considering building a light rail transit (LRT) system similar to the...
The City of G is considering building a light rail transit (LRT) system similar to the one recently constructed in City KW. You have been asked to conduct a cost benefit analysis of the project. You have some data about the KW LRT project: Present value of annual net benefits (to KW residents) =$620 million Construction costs (paid by KW residents) (t=0) =$820 million Grant from the provincial government (t=0) =$300 million Grant from the federal government (t=0) =$250 million...
A city is deciding whether it makes sense to invest in a light rail line. Engineers...
A city is deciding whether it makes sense to invest in a light rail line. Engineers have projected that if the rail line were to be built, once completed it would reduce travel time for 2,000 commuters by 60 minutes per day (for each workday). The line will take four years to build. The costs of construction are projected to equal $25,000,000 per year, and the costs of operating the line are assumed to equal $2,000,000 per year. Assume that...
Oregon Transportation Inc. (OTI) has just signed a contract to purchase light rail cars from a...
Oregon Transportation Inc. (OTI) has just signed a contract to purchase light rail cars from a manufacturer in Germany for €2,500,000. The purchase was made in June with payment due six months later in December. Because this is a sizable contract for the firm and because the contract is in euros rather than dollars, OTI is considering several hedging alternatives to reduce the exchange rate risk arising from the sale. To help the firm make a hedging decision you have...
The urban tram project, which operates with a light rail system, is planned. In addition to...
The urban tram project, which operates with a light rail system, is planned. In addition to metaformic, sedimentary and magmatic rocks on the ground, unconsolidated fine sand-silt grain size ground materials were also found. Underground water level depth is between 1 and 3 meters. There is a fault zone along the project line. What can be the geotechnical problems that may be encountered before, during and after the project construction, and solutions as a civil engineer?
Three transportation improvement plans have been proposed for heavily populated and congested city. Alternative I –...
Three transportation improvement plans have been proposed for heavily populated and congested city. Alternative I – upgrading of congested signalised intersections into full grade separated intersections at an initial construction cost of $180 million and a salvage value of $22 million. Annual operation and maintenance costs will be $230,000 per year. Major maintenance in year 20 at $5 million and in year 40 at $8 million. Alternative II - upgrading of bus service to BRT system at an initial cost...
A shopping center project is proposed to the city council. It cannot be built unless a...
A shopping center project is proposed to the city council. It cannot be built unless a zoning change is approved by the council. The planning board must first make a recommendation, for or against the zoning change, to the council. Let A1 = city council approves the zoning change A2 = city council disapproves the change The prior is: Pr(A1) = .7,   Pr(A2) = .3 Let B denote the event of a negative recommendation by the planning board. Past history...
The City of Windsor is getting frustrated with AEMI's proposed project. Nothing seems to be happening...
The City of Windsor is getting frustrated with AEMI's proposed project. Nothing seems to be happening because stakeholders cannot agree on anything, and AEMI's managers in New York are not responding to the City's questions. The City's engineers and planners suggest that a benefit cost analysis for Windsor can show which project (wind or solar) will be the best from a public perspective Effects Photovoltaic Production Facilit Oil Storage/Transfer Facility Number of displaced families 2 households 35 households Annual tax...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT