Question

In: Accounting

Fixed and Variable Cost Allocation Kumar, Inc., evaluates managers of producing departments on their ability to...

Fixed and Variable Cost Allocation

Kumar, Inc., evaluates managers of producing departments on their ability to control costs. In addition to the costs directly traceable to their departments, each production manager is held responsible for a share of the costs of a support center, the Human Resources (HR) Department. The total costs of HR are allocated on the basis of actual direct labor hours used. The total costs of HR and the actual direct labor hours worked by each producing department are as follows:

           Year 1 Year 2
Direct labor hours worked:
    Department A 33,000 34,000
    Department B 36,000 34,000
Total hours 69,000 68,000
Actual HR cost $122,250 $122,250
Budgeted HR cost 117,250* 117,000*

*$0.25 per direct labor hour plus $100,000.

When the capacity of the HR Department was originally established, the normal usage expected for each department was 18,000 direct labor hours. This usage is also the amount of activity planned for the two departments in Year 1 and Year 2.

Required:

1. Allocate the costs of the HR Department using the direct method and assuming that the purpose is product costing.

Department A Department B
Variable costs $ $
Fixed costs
Total cost $ $

2. Allocate the costs of the HR Department using the direct method and assuming that the purpose is to evaluate performance.

Year 1 Year 2
Department A Department B Department A Department B
Variable costs $ $ $ $
Fixed costs
Total cost $ $ $ $

Solutions

Expert Solution

1)

Allocation of HR Costs of the Department using Direct Method:

Department A Department 2
Variable Costs ($10,761 + $11,250); ($11,739 + $11,250) $22,011 $22,989
Fixed Costs ($47,826 + $50,0000; ($52,174 + $50,000) $97,826 $102,174
Total Cost $119,837 $125,163

Working notes:

Year 1
Department A Department 2 Total
Variable Costs ($122,500 - $100,000 = $22,500*33,000/69,000 hours); ($22,500*36,000/69,000 hours) $10,761 $11,739 $22,500
Fixed Costs ($100,000*33,000/69,000 hours); ($100,000*36,000/69,000) $47,826 $52,174 $100,000
Total Costs $58,587 $63,913 $122,500
Year 2
Department A Department 2 Total
Variable Costs ($122,500 - $100,000 = $22,500*34,000/68,000 hours); ($22,500*34,000/68,000 hours) $11,250 $11,250 $22,500
Fixed Costs ($100,000*34,000/68,000 hours); ($100,000*34,000/68,000) $50,000 $50,000 $100,000
Total Costs $61,250 $61,250 $122,500

2)

Allocation of costs of the HR Department using direct method for evaluation purpose:

Year 1 Year 2
Department A Department 2 Department A Department 2
Variable Costs ($122,500 - $100,000 = $22,500*33,000/69,000 hours); ($22,500*36,000/69,000 hours) | ($122,500 - $100,000 = $22,500*34,000/68,000 hours); ($22,500*34,000/68,000 hours) $10,761 $11,739 $11,250 $11,250
Fixed Costs ($100,000*33,000/69,000 hours); ($100,000*36,000/69,000) | ($100,000*34,000/68,000 hours); ($100,000*34,000/68,000) $47,826 $52,174 $50,000 $50,000
Total Costs $58,587 $63,913 $61,250 $61,250

Related Solutions

Fixed and Variable Cost Allocation Kumar, Inc., evaluates managers of producing departments on their ability to...
Fixed and Variable Cost Allocation Kumar, Inc., evaluates managers of producing departments on their ability to control costs. In addition to the costs directly traceable to their departments, each production manager is held responsible for a share of the costs of a support center, the Human Resources (HR) Department. The total costs of HR are allocated on the basis of actual direct labor hours used. The total costs of HR and the actual direct labor hours worked by each producing...
Blueprint Problem: Support Department Cost Allocation The Difference Between Support Departments and Producing Departments When a...
Blueprint Problem: Support Department Cost Allocation The Difference Between Support Departments and Producing Departments When a firm decides that a plant wide overhead rate is not sufficient (perhaps it makes multiple products and the various products go through some processes but not all), it may decide to departmentalise. The factory is divided into departments and costs are accumulated within the departments. When that is done, there are basically two types of departments: producing departments that actually make units of product,...
Scenario: The fixed cost of producing 500 units of Good Y is $25,000, while the variable...
Scenario: The fixed cost of producing 500 units of Good Y is $25,000, while the variable cost of producing 500 units of Good Y is $60,000. 1. __________ Refer to the scenario above. If the market for Good Y is monopolistically competitive, a firm producing Good Y will shut down production in the short run if price falls below ________. A) $60 B) $200 C) $120 D) $50 2. __________ Refer to the scenario above. Which of the following will...
1.) The table below represents the costs of producing jackets. Quantity Fixed Cost Variable Cost Total...
1.) The table below represents the costs of producing jackets. Quantity Fixed Cost Variable Cost Total Cost Average Fixed Cost Average Variable Cost Average Total Cost 12 $118 $25 $143 ? ? ? 18 $118 $50 $168 ? ? ? 26 $118 $75 $193 ? ? ? 34 $118 $100 $218 ? ? ? 42 $118 $125 $243 ? ? ? Find the average variable cost for producing 42 jackets. Round your answer to the nearest hundredth. 2.) The table...
quantity of broomsticks fixed cost variable cost total cost average fixed cost average variable cost average...
quantity of broomsticks fixed cost variable cost total cost average fixed cost average variable cost average total cost marginal cost marginal product 0 10 $13 $38 22 $28 32 $70 41 $64 50 $110 59 $108 65 $133 70 $185 how do I fill in the blanks? as well as graph the three average cost curves and the marginal cost curve.
The following information is departmental cost allocation with two service departments and two production departments. Percentage...
The following information is departmental cost allocation with two service departments and two production departments. Percentage Service Provided to Department Cost S1 S2 P1 P2 Service 1 (S1) $ 30,000 0 % 30 % 35 % 35 % Service 2 (S2) 20,000 20 0 20 60 Production 1 (P1) 100,000 Production 2 (P2) 150,000 REQ1. What is the amount of service department cost allocated to P1 and P2 using the direct method? REQ2. What is the total cost in P1...
The following information is departmental cost allocation with two service departments and two production departments. Percentage...
The following information is departmental cost allocation with two service departments and two production departments. Percentage Service Provided to Department Cost S1 S2 P1 P2 Service 1 (S1) $ 42,000 0 % 25 % 45 % 30 % Service 2 (S2) 32,000 20 0 20 60 Production 1 (P1) 220,000 Production 2 (P2) 270,000 What is the amount of service department cost allocated to P1 and P2 using the direct method?
Variable and Fixed Cost Behavior
Munchak Company’s relevant range of production is between 9,000 and 11,000 units. Last month the company produced 10,000 units. Its total manufacturing cost per unit produced was $70. At this level of activity the company’s variable manufacturing costs are 40% of its total manufacturing costs.Required:Assume that next month Munchak produces 10,050 units and that its cost behavior patterns remain unchanged. Label each of the following statements as true or false with respect to next month. Do not use a calculator...
2. Describe a fixed cost, variable cost. Explain why the variable and fixed costs are important...
2. Describe a fixed cost, variable cost. Explain why the variable and fixed costs are important in cost accounting. Give your opinion
Cost is classified on the basis of behaviour as fixed cost, variable cost and semi-variable cost....
Cost is classified on the basis of behaviour as fixed cost, variable cost and semi-variable cost. You are required to explain these 3 elements of cost with an example in an engineering organization
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT