Question

In: Civil Engineering

A low-rise is being planned and your company provided the most advantageous bid to the owner,...

A low-rise is being planned and your company provided the most advantageous bid to the owner, as a contractor in the design build partnership you have been tasked to begin working with the design team on all electrical components of the structure. Develop a list of all of the required electrical systems in the structure, assume this is a high hazard structure. Include in your check list any items that would require long lead times, special considerations (location, etc.), and any possible input from the owner, the list needs to be extensive in nature such that the design team can begin concept design from your list.

Solutions

Expert Solution

The design data required for feasibility designs is-

  1. Availability of electric power for construction and for O&M.
  2. For existing non-Reclamation powerplants and pumping plants, single-line diagrams and switching diagrams that include equipment ratings will be necessary for a proper evaluation of existing equipment within the scope of any proposed feasibility or specifications design.
  3. Source of electricity: location of the point where the connection to power utility will be made, the capacity, and type (single phase/three phase).
  4. Location of existing transformers.
  5. Route of proposed distribution lines and whether they are to be overhead or underground.
  6. Plant uprating (powerplant): Design data should include, as a minimum, a description of the hydrologic and hydraulic conditions and anticipated increase in power capacity and/or energy. The data should also include recommendations regarding the expected means (machine addition or machine rebuilding) of achieving the uprate.
  7. Switchyards and substations
  8. Transmission lines
  9. An alternative power source
  10. Tunnels-Requirements for installation of power, lighting or telemetering cables in tunnel.

The following items should be considered in preparing the above data:

(a) Need for replacement of any existing major power equipment due to age or deterioration (generator winding and core, power transformers, power circuit breakers, switchgear, station service equipment, etc.).

(b) Changes in operation of the plant, such as from base load to peaking load operation; changes in upstream or downstream storage; and changes in irrigation demands.

(c) Environmental and recreational impacts resulting from changes in water release through the plant. Identify proposed mitigation measures if appropriate.

(d) Recommendation/need or to replace existing rotating exciter/voltage regulator with static excitation system.

(e) Recommendation/need to replace existing mechanical governor with a digital system.

The following is a list of data requirements for specifications designs, in addition to data requested for feasibility designs.

(1)Names, telephone numbers, Web sites, and email addresses of electrical power suppliers and contacts within those organizations.

(2) Source and voltage of incoming power including construction power.

(3) Location of point where connection to power supply will be made.

(4) Estimated electrical peak load.

(5) State and local code requirements.

(6) System voltage at which power will be supplied, number of phases, and whether service will be overhead or underground.

(7) Dates when power will be available.

(8) Latest as-built drawings for existing power equipment, controls, protection, and indication/annunciation circuitry.


Related Solutions

Write a short letter to the owner stating your companies intention to bid the job and...
Write a short letter to the owner stating your companies intention to bid the job and name one specific idea to improve or "value engineer" the project. These projects often are tight budget-wise, so it is not uncommon for contractors to work with the engineers to get the best possible outcome for the owner.
Calculating a Bid Price Your company has been approached to bid on a contract to sell...
Calculating a Bid Price Your company has been approached to bid on a contract to sell 15,000 voice recognition (VR) computer keyboards a year for four years. Due to technological improvements, beyond that time they will be outdated and no sales will be possible. The equipment necessary for the production will cost $3.4 million and will be depreciated on a straight-line basis to a zero salvage value. Production will require an investment in net working capital of $75,000 to be...
Problem 8-34 Calculating a Bid Price Your company has been approached to bid on a contract...
Problem 8-34 Calculating a Bid Price Your company has been approached to bid on a contract to sell 3,900 voice recognition (VR) computer keyboards a year for four years. Due to technological improvements, beyond that time they will be outdated and no sales will be possible. The equipment necessary for the production will cost $3.5 million and will be depreciated on a straight-line basis to a zero salvage value. Production will require an investment in net working capital of $92,000...
Brewster’s Used Cars, Inc. employs several salespeople. Brewster, the owner of the company, has provided a...
Brewster’s Used Cars, Inc. employs several salespeople. Brewster, the owner of the company, has provided a file that contains sales records for each salesperson for the past month. Each record in the file contains the following two fields: The salesperson’s ID number, as an integer The amount of a sale, as a real number The records are already sorted by salesperson ID. Brewster wants you to design a program that prints a sales report. The report should show each salesperson’ssales...
If you were a small business owner would you want to most of your costs fixed...
If you were a small business owner would you want to most of your costs fixed or variable?
-Giving reasons for your answer based on the type of system being developed, suggest the most...
-Giving reasons for your answer based on the type of system being developed, suggest the most appropriate generic software process model that might be used as a basis for managing the development of the following systems: -A system to control anti-lock braking in a car -A virtual reality system to support software maintenance -A university accounting system that replaces an existing system -An interactive travel planning system that helps users plan journeys with the lowest environmental impact.
describe the most difficult-to-deal waste that is being produced in your household and suggest how to...
describe the most difficult-to-deal waste that is being produced in your household and suggest how to treat it
Walmart is the most common low-active price strategy company. They use this approach to focus on...
Walmart is the most common low-active price strategy company. They use this approach to focus on offering everyday low prices. The main advantage of this strategy is that it is simple for the company and the consumer. The company does not have to incur higher costs on managing and trying to analyze a complex cost model and can save time and money with a more manageable advertising plan. In regards to the customer, they can count on the low price...
Some company produces two products, A and B with most of the production being accomplished by...
Some company produces two products, A and B with most of the production being accomplished by machine. Data on operations and costs for October follow: Product A Product B Total   Units produced 9,000 4,600 13,600   Machine-hours used 970 820 1,790   Direct labor-hours 210 120 330   Direct materials costs $ 12,100 $ 7,200 $ 19,300   Direct labor costs $ 4,200 $ 2,400 $ 6,600   Manufacturing overhead costs $ 22,423 Management asks the firm's cost accountant to compute product costs. The accountant...
The owner of a moving company usually has her most experienced manager predict the total number...
The owner of a moving company usually has her most experienced manager predict the total number of labor hours required to complete a move. While useful, the owner is interested in a more accurate method of predicting the number of labor hours required. As a preliminary effort, data was collected on the number of work hours required to complete a move, number of cubic feet moved, the number of large pieces, and if an elevator was present. How much correlation...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT