In: Civil Engineering
Answer the following question:
a) What is the main difference between the CM and CM at risk
contracts?
b) Write the general format (equation) for each type of the
negotiated contract
c) If free float = 6 and total float = 5, explain the meaning of
these 2 numbers?
d) How to prepare the detailed Estimate?
e) During what period a contractor can withdraw the bid without
penalty?
f) What is the project triangle? Explain the effect of increase of
each one on the others?
g) What are the main steps used to estimate the total project
cost?
h) List the four items that need to be identified when planning for
WBS?
a. CM - The construction
manager is the person who is an agent of the owner. A CM-Agent
helps the owner to make critical decisions about a project but does
not actually commited to delivering the project under the
boundations.
CM at risk Contracts - Construction management
“at-risk" is the situation where the construction manager is
legally responsible for delivering the project on-time and
on-budget and subcontracting for timely payments down the
chain.
b. The General format of negosiation include these point -
1. Issue Identification- Identify the issues you want to
negotiate like read the suppliers offer, write down down notes
about part that are important.
2. Issue Information- Have proper information about each issue that
you want to negotiate.
3. Classify the Issues- Classify the sections as Negotiable and
Non-Negotiable.
4. Prepare the meeting agenda - Outline your issues and highlight
any issues they may have with your contract.
5. Get ready to Negotiate- Understand the most important things
before going to the negotiation table.
6.Negotiation Meeting - This is proper meeting in which you will
sit down with the supplier and neggotiate on all the topics.
7. Summarise all points- Here you simply divide this into 2
categories: Points that you have agreed and Points that you or the
other side would need to get back to each other.
c. Total Float is 5 that means that an activity can be delayed by 5 days from its early start date without delaying the project's finish date.
Free Float is 6 that means a schedule activity can be delayed by 6 days without delaying the early start date of any immediately following schedule activities.
d. The preparations of detailed construction
estimate includes estimating the quantities of various items of
work and then calculating the cost of each item.
Detailed estimate is prepared in two stages -
i) Details of measurements and calculation of quantities: In this
the complete work is divided into various items of work like
earthwork,concreting, plastering etc.
The details of measurements are taken from drawings and calculate
the quantity of each and every item.
ii) Abstract of Estimated Cost: The cost of each item of work is
worked out from the quantities that are calculated above at
workable rates and get the total cost of the project.