Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory.
In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months:
Month | ||||||||
1 | 2 | 3 | 4 | |||||
Quality control measures: | ||||||||
Number of defects | 185 | 163 | 124 | 91 | ||||
Number of warranty claims | 46 | 39 | 30 | 27 | ||||
Number of customer complaints | 102 | 96 | 79 | 58 | ||||
Material control measures: | ||||||||
Purchase order lead time | 8 days | 7 days | 5 days | 4 days | ||||
Scrap as a percent of total cost | 1 | % | 1 | % | 2 | % | 3 | % |
Machine performance measures: | ||||||||
Machine downtime as a percentage of availability | 3 | % | 4 | % | 4 | % | 6 | % |
Use as a percentage of availability | 95 | % | 92 | % | 89 | % | 85 | % |
Setup time (hours) | 8 | 10 | 11 | 12 | ||||
Delivery performance measures: | ||||||||
Throughput time | ? | ? | ? | ? | ||||
Manufacturing cycle efficiency (MCE) | ? | ? | ? | ? | ||||
Delivery cycle time | ? | ? | ? | ? | ||||
Percentage of on-time deliveries | 96 | % | 95 | % | 92 | % | 89 | % |
The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures:
Average per Month (in days) |
||||
1 | 2 | 3 | 4 | |
Wait
time per order before start of production |
9.0 | 11.5 | 12.0 | 14.0 |
Inspection time per unit | 0.8 | 0.7 | 0.7 | 0.7 |
Process time per unit | 2.1 | 2.0 | 1.9 | 1.8 |
Queue time per unit | 2.8 | 4.4 | 6.0 | 7.0 |
Move time per unit | 0.3 | 0.4 | 0.4 | 0.5 |
Required:
1-a. Compute the throughput time for each month.
1-b. Compute the manufacturing cycle efficiency (MCE) for each month.
1-c. Compute the delivery cycle time for each month.
3-a. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE.
3-b. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE.
Ans. | Throughput Time | Manufacturing | Delivery Cycle | |||
Months | Cycle Efficiency | Time | ||||
1 | 6 | days | 35.0% | 15 | days | |
2 | 7.5 | days | 26.67% | 19 | days | |
3 | 9 | days | 21.11% | 21 | days | |
4 | 10 | days | 18.00% | 24 | days | |
*Calculations for 1 a, b, c are shown below: | ||||||
Ans. 1 a | Throughput time = Move time + Process time + Queue time + Inspection time | |||||
Months | ||||||
Particulars | 1 | 2 | 3 | 4 | ||
Move time per unit | 0.3 | 0.4 | 0.4 | 0.5 | ||
Process time per unit | 2.1 | 2 | 1.9 | 1.8 | ||
Inspection time per unit | 0.8 | 0.7 | 0.7 | 0.7 | ||
Queue time | 2.8 | 4.4 | 6 | 7 | ||
Total (Throughput Time) | 6 days | 7.5 days | 9 days | 10 days | ||
Ans. 1 b | Manufacturing cycle efficiency = Process time or value added time / Throughput time * 100 | |||||
Months | ||||||
1 | 2.1 / 6 *100 | 35.0% | ||||
2 | 2 / 7.5 *100 | 26.67% | ||||
3 | 1.9 / 9 * 100 | 21.11% | ||||
4 | 1.8 / 10 * 100 | 18.00% | ||||
Ans. 1 c | Delivery cycle time = Throughput time + Wait time per order before start of production | |||||
Months | ||||||
1 | 9 + 6 | 15 | days | |||
2 | 11.5 + 7.5 | 19 | days | |||
3 | 12 + 9 | 21 | days | |||
4 | 14 + 10 | 24 | days | |||
Ans. 3 | Month 5 | Month 6 | ||||
Throughput time | 3 days | 2.3 days | ||||
Manufacturing cycle efficiency (MCE) | 60.00% | 78.26% | ||||
*Calculations: | ||||||
Ans. 3 a | Month 5 : | |||||
Throughput time: | ||||||
Move time per unit | 0.5 | |||||
Process time per unit | 1.8 | |||||
Inspection time per unit | 0.7 | |||||
Total | 3 | days | ||||
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100 | ||||||
1.8 / 3 * 100 | ||||||
60.00% | ||||||
Ans. 3 b | Month 6 : | |||||
Throughput time: | ||||||
Move time per unit | 0.5 | |||||
Process time per unit | 1.8 | |||||
Total | 2.3 | days | ||||
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100 | ||||||
1.8 / 2.3 * 100 | ||||||
78.26% | ||||||