Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $892,800 is estimated to result in $297,600 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $130,200. The press also requires an initial investment in spare parts inventory of $37,200, along with an additional $5,580 in inventory for each succeeding year of the project. |
Required : |
If the shop's tax rate is 33 percent and its discount rate is 8 percent, what is the NPV for this project? (Do not round your intermediate calculations.) |