In: Civil Engineering
Mr.XXXXXX is planning to construct a 3 storey apartment building
in Muscat area, what are the
drawings to be submitted to get a major building permit as per
Muscat building regulation Local Order
No. 23/92
The following set of drawings shuld be submitted in order to get a Major Building Permit from Muscat building regulation Local Order No. 23/92
- Horizontal plan for each floor showing the thickness of external andinternal walls and openings. Also the dimension and use of all elements, units and space within the floor and the design information needed for implementation. A horizontal plan, for half of the floor, may be submitted if the building is symmetrical i.e the symmetry axis passes through the main entrance.
- Vertical plans (facades/elevation). The vertical plan shall show the openings, internal and external projections and other elements of the facade/elevation. Also the details and information needed for implementation plans of two facades/elevations, minimum, shall be submitted.
- An architectural, section (cross or longitudinal) from the highest level in the building to slightly below the ground level showing elements of the building, levels of roofs, openings, floors and the main building material. Applicants shall submit more than one section if so required by the Municipality.
-A horizontal plan for the foundations, columns and ground beams showing all the necessary dimensions, calculation tables and other details needed for checking and implementation.