You need to develop a preliminary estimate for a 5” thick, Heavy Industrial, Reinforced Concrete Slab...

You need to develop a preliminary estimate for a 5” thick, Heavy Industrial, Reinforced Concrete Slab on Grade. What are the costs/SF for material, installation, and total for this slab on grade construction? What is the total cost if the slab on grade is 80,000 SF?

Solutions

Expert Solution

Due to the problematic question, the answer solved with handwritting and attached for your reference please.

1. Cost for 943.89 cu/m grade concrete is Rs. 4,719,450.00 (Assuming Rs.5000.00 per cu/m)

2. Cost for 70.79 tonnes of steel is Rs. 3,114,837.00 (Assuming Rs. 44,000.00/tonne)

3. Cost for total shuttering including steel installation is Rs. 3,600,000.00 (Assuming Rs.45.00/Sf)

So, total cost is Rs. 11,434,287.00 for casting the grade concrete of 80,000sf with 5'' .


Related Solutions

Performance of Reinforced Concrete Slab due to Reinforcement Corrosion
Performance of Reinforced Concrete Slab due to Reinforcement Corrosion
Design and draw the final cross section of a one-way reinforced concrete slab for the inside...
Design and draw the final cross section of a one-way reinforced concrete slab for the inside of a building, where the span is l =3,6 m, and the applied live load is   LL = 7,02 KN m2 ⁄ . Normal-weight aggregate concrete is specified with a density of 23. 5 KN m3 ⁄(reinforcement weight is included). Use the largest of claculated steel ratio ρ and 0.75ρmax. Assume: Es = 2 × 105 MPa, fc′ = 28 MPa and fy =...
1-A building requires a 100-foot long by 83-foot wide by 5-inch thick concrete slab. Using a...
1-A building requires a 100-foot long by 83-foot wide by 5-inch thick concrete slab. Using a waste factor of 10 %, Include calculations. a)determine the number of cubic yards of concrete needed to pour the slab. (2 points) 2-Determine the number of rolls of wire mesh needed if there are 750 SF of wire per roll and 12% of waste. Include calculations. (2 points) 9 BCT 2770 Estimating Fundamentals 3-Determine the amount of rebar needed for the slab if it...
prestressed road bridge of span 16.74 m consists of a concrete slab of 420 mm thick...
prestressed road bridge of span 16.74 m consists of a concrete slab of 420 mm thick with parallel post-tensioned cables, in each of which the force at transfer is 440 kN. If the bridge is required to support a uniformly distributed applied load of 43.37kN/m2 , with tensile stress in the concrete not exceeding 0.85 N/mm2 at any time. Calculate the maximum horizontal spacing of the cables, their distance from the soffit of the slab at mid-span and their lowest...
Design a simply supported one-way reinforced concrete floor slab to span 10 ft and carry a...
Design a simply supported one-way reinforced concrete floor slab to span 10 ft and carry a service live load of 175 psf and a service dead load of 25 psf (the dead load does not include the self-weight of the slab). Use f’c = 3000 psi and Fy = 60,000 psi. Make the slab thickness to 1/2-in. increments.
i need a research about the main usage of reinforced concrete structure including it's applications and...
i need a research about the main usage of reinforced concrete structure including it's applications and primary advantages and disadvantages additionally , discuss the main types of each structural elements such slaps, beams , columns and foots
You are now an adviser to President Obama. You need to give him 5 concrete suggestions...
You are now an adviser to President Obama. You need to give him 5 concrete suggestions on fiscal policy and monetary policy in an effort to get the economy to continue to improve. Give your suggestions and explain why you think your choices are good choices.
You are now an adviser to President Obama. You need to give him 5 concrete suggestions...
You are now an adviser to President Obama. You need to give him 5 concrete suggestions on fiscal policy and monetary policy in an effort to get the economy to continue to improve. Give your suggestions and explain why you think your choices are good choices. (500 words minimum)
What do you and your audit team need to consider when making the preliminary assessment of...
What do you and your audit team need to consider when making the preliminary assessment of materiality?
What are the steps in detail that you need for the industrial production of an enzyme...
What are the steps in detail that you need for the industrial production of an enzyme that is a membrane bound protein, of which molecular weight is 90 KD and surface charge is positive? Add hand drawn picture as many as possible and confirm the amount of enzyme by ELISA and Western blot.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT