In: Finance
Knotts, Inc., an all-equity firm, is considering an investment of $1.82 million that will be depreciated according to the straight-line method over its four-year life. The project is expected to generate earnings before taxes and depreciation of $608,000 per year for four years. The investment will not change the risk level of the firm. The company can obtain a four-year, 8.8 percent loan to finance the project from a local bank. All principal will be repaid in one balloon payment at the end of the fourth year. The bank will charge the firm $58,000 in flotation fees, which will be amortized over the four-year life of the loan. If the company financed the project entirely with equity, the firm’s cost of capital would be 12 percent. The corporate tax rate is 22 percent. |
Using the adjusted present value method, calculate the APV of the project. (Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, rounded to 2 decimal places, e.g., 1,234,567.89) |
Solution:
The adjusted present value of a project equals the net present value of the project under all-equity financing and the net present value of any financing side effects.
APV = NPV (All-equity) + NPV (Financing side effects)
First, we calculate the NPV (All-equity)
NPV (All-equity) =-Initial Investment + PV [(1 - tax rate) (Earnings before taxes and depreciation)] + PV (Depreciation tax shield)
NPV (All-equity) = -$1,820,000 + (1 - 0.22) ($608,000) (PVIFA @ 12%, 4) + ($1,820,000/4) (0.22) (PVIFA @ 12%, 4)
NPV (All-equity) = -$1,820,000 + 1,440,433 + 304,038.7
NPV (All-equity) = -$75528.80
Now, we find NPV (Financing side effects)
NPV (financing side effects) = Proceeds, net of flotation costs - After-tax PV (Interest payments) - PV (Principal payments) + PV(Flotation cost tax shield)
NPV (financing side effects) = ($1,820,000 - $58,000/4) - (1 - 0.22) (0.088) ($1,820,000)(PVIFA @ 8.80%, 4) - [$1,820,000/1.088^4] + (0.22) ($58,000/4)(PVIFA @ 8.80%, 4)
NPV (financing side effects) = $1,834,500 - 406,504.4 - 1,298,840 + 10,380.24
NPV (financing side effects) = $139,535.3
Therefore,
APV = -$75,528.8+ $139,535.3
APV = $64,006.56
Since the adjusted present value (APV) is positive, Knotts should undertake the project.