In: Accounting
You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control.
After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March:
Cost Formula | Actual Cost in March | ||
Utilities | $16,700 + $0.12 per machine-hour | $ | 20,420 |
Maintenance | $38,600 + $1.40 per machine-hour | $ | 54,800 |
Supplies | $0.30 per machine-hour | $ | 4,600 |
Indirect labor | $94,400 + $1.10 per machine-hour | $ | 112,900 |
Depreciation | $68,500 | $ | 70,200 |
During March, the company worked 14,000 machine-hours and produced 8,000 units. The company had originally planned to work 16,000 machine-hours during March.
Required:
1. Calculate the activity variances for March.
2. Calculate the spending variances for March.
Answer 1 - Activity variances for March
Budgeted Costs in March for 16000 units | Budgeted Costs in March for 14000 units | Activity variances | ||
Utilities | $ 18,620 | $ 18,380 | $ 240 | F |
Maintenance | $ 61,000 | $ 58,200 | $ 2,800 | F |
Supplies | $ 4,800 | $ 4,200 | $ 600 | F |
Indirect labor | $ 112,000 | $ 109,800 | $ 2,200 | F |
Depreciation | $ 68,500 | $ 68,500 | $ - | F |
Total | $ 264,920 | $ 259,080 | $ 5,840 | F |
Answer 2 - Spending variances for
March.For above part, machine hours are taken as
16,000 hours.
Budgeted Costs in March | Actual Cost in March | Activity variances | ||
Utilities | $ 18,380 | $ 20,420 | $ 2,040 | U |
Maintenance | $ 58,200 | $ 54,800 | $ 3,400 | F |
Supplies | $ 4,200 | $ 4,600 | $ 400 | U |
Indirect labor | $ 109,800 | $ 112,900 | $ 3,100 | U |
Depreciation | $ 68,500 | $ 70,200 | $ 1,700 | U |
Total | $ 259,080 | $ 262,920 | $ 3,840 | U |
For the above part, machine hours are taken as 14,000 hours.
In case of any doubt, please comment.