Question

In: Operations Management

Question 3 The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts...

Question 3

  1. The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates as follows:

Time

Estimates

(weeks)

Activity

Description

Predecessor

a

m

b

A

Position Recruiting

-

5

8

17

B

System Development

-

3

12

15

C

System Training

A

4

7

10

D

Equipment training

A

5

8

23

E

Manual System Test

B, C

1

1

1

F

Preliminary System Changeover

B, C

1

4

13

G

Computer-Personnel Interface

D, E

3

6

9

H

Equipment Modification

D, E

1

2.5

7

I

Equipment testing

H

1

1

1

J

System Debugging and Installation

F, G

2

2

2

K

Equipment Changeover

G, I

5

8

11

Use the information in the table to answer the following questions

  1. Compute the expected activity completion time for each activity. (3 marks)
  2. Draw the project network diagram together with the activity schedule. (5 marks)
  3. When will the computerized accounting system be ready for use? (1 mark)
  4. What is the critical path (the critical activities)? (2 marks

b.Management of CBG is not happy with the completion time in Question 2(iii) and wants the project completed earlier than that. You are given the following additional activity information.

Activity

Crash Time (weeks)

Activity Cost (GH¢)

Normal

Crash

A

7

4,800

6,300

B

9

9,100

15,500

C

5

3,000

4,000

D

8

3,600

5,000

E

1

0

0

F

3

1,500

2,000

G

5

1,800

2,000

H

3

0

0

I

1

0

0

J

2

0

0

K

6

5,000

7,000

i. Prepare a table of Allowable Crash Time and Crash Cost per Week for each activity. (5 marks)

Management of CBG can offer a maximum of GH¢800 per week to enable the project manager reduce the project completion time:

ii. prepare a table for the crashing procedure. (5.5 marks)

iii. when will the project now be completed? (0.5 mark)

iv. what is the total extra cost to management of CBG? (1 mark)

v. If management of CBG wishes the computerized accounting system to be ready at week 30, what will be the total extra cost to CBG? (2 marks

Solutions

Expert Solution

ANSWER 3 A=

Answer i=

Activity a m b Completion time Completion time ( whole number)
A 5 8 17 (5+4*8+17)/6 9.00
B 3 12 15 (3+4*12+15)/6 11.00
C 4 7 10 (4+4*7+10)/6 7.00
D 5 8 23 (5+4*8+23)/6 10.00
E 1 1 1 (1+4*1+1)/6 1.00
F 1 4 13 (1+4*4+13)/6 5.00
G 3 6 9 (3+4*6+9)/6 6.00
H 1 2.5 7 (1+4*2.5+7)/6 3.00
I 1 1 1 (1+4*1+1)/6 1.00
J 2 2 2 (2+4*2+2)/6 2.00
K 5 8 11 (5+4*8+11)/6 8.00

Answer ii-

Activity ES EF LS LF
A 0 9 0 9
B 0 11 7 18
C 9 16 11 18
D 9 19 9 19
E 16 17 18 19
F 16 21 20 25
G 19 25 19 25
H 19 22 23 26
I 22 23 26 27
J 25 27 25 27
K 27 35 27 35

Answer iii= The computerized system will be ready to use after 9+10+6+2+8=35 weeks (which is the duration of the critical path)

Answer iiv= The critical path = longest path = A-D-G-J-K

P.S. AS PER CHEEGG ONLY FIRST 4 PARTS CAN BE ANSWERED.


Related Solutions

The Farmer’s American Bank of Leesburg is planning to install a new computerized accounts system. Bank...
The Farmer’s American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates as follows: TIME ESTIMATES (WEEKS) ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR a m b A Position recruiting — 5 8 17 B System development — 3 12 15 C System training A 4 7 10 D Equipment training A 5 8 23 E Manual system test...
M5_A2. The Mountaineers American Bank of Carolina is planning to install a new computerized accounts system....
M5_A2. The Mountaineers American Bank of Carolina is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and the activity time estimates, as shown in the table below. activity optim time (a) most likely time (m) pessim time (b) immediate Pred A 5 8 17 --- B 3 12 15 --- C 4 7 10 A D 5 8 23 A E 1 1...
Question No. 3 Atlas Engineering is planning to install new machinery in their manufacturing division. The...
Question No. 3 Atlas Engineering is planning to install new machinery in their manufacturing division. The total investment budget is $120000. Atlas Engineering is reviewing three machinery that will generate three different cash inflow with the similar investment. For comparison and optimal capital budgeting decision, company require to analyze three project options with the following cash inflows. Year Project A Inflow Project B Inflow Project C Inflow 1 $29,064 $31,970 $34,877 2 33,960 $37,356 $40,752 3 30,600 $33,660 $36,720 4...
Question 3 (a) The business objective of the director of planning of Game Ghana is to...
Question 3 (a) The business objective of the director of planning of Game Ghana is to forecast monthly sales for all new stores, based on the number of profiled customers who live no more than 30 minutes from a Game store. To examine the relationship between the number of profiled customers who live within a fixed radius from a Game store and its monthly sales, data were collected from a sample of 10 stores: Store No. of Customers (‘000) Monthly...
The city of Stillwater is planning to install a new settling tank as an upgrade to...
The city of Stillwater is planning to install a new settling tank as an upgrade to their existing water treat plant. You run a batch settling test using a 2.0 m column and coagulated water from their existing tank and collect the following data (Table 1). Using this data, design a settling tank to remove 65% of the influent suspended solids. Assume a design flow of 0.5 m3/s. Use scale up factors of 0.65 for overflow rate and 1.75 for...
Question 3 You are the manager of Zokia Ghana Limited, a producer of beans. In Ghana,...
Question 3 You are the manager of Zokia Ghana Limited, a producer of beans. In Ghana, it is possible to produce beans or groundnut using the same resources. Therefore, producers are able to switch from beans to groundnut production depending on market conditions. Consequently, Zokia Ghana Limited consulted an Economist who estimated the demand function for beans as: ?? ? = 600 − 4?? − 0.03? − 12? ? + 15? + 6?? + 1.5? where ?? ? is the...
Please provide the answers in clear way A company is planning to install a new automated...
Please provide the answers in clear way A company is planning to install a new automated plastic-molding press. Four different presses are available. The initial capital investments and annual expenses for these four different alternatives are: Press P1 P2 P3 P4 Capital Investment $24,000 $30,400 $49,600 $52,000 Annual expenses $31,200 $29,100 $25,200 $22,900 Press life (years) 5 5 5 5 Assume each press has the same output capacity of 150,000 units per year, has no salvage value at the end...
QUESTION Over the last few months, the Bank of Ghana ( has cracked the whip at...
QUESTION Over the last few months, the Bank of Ghana ( has cracked the whip at the banking industry in a bid to restore sanity in the industry. In August 2017, the UT and Capital Banks were liquidated for failing to meet the bank of Ghana’s minimum capital ratio. The operations of UniBank, Royal Bank, Beige Bank, Sovereign Bank, and Construction Bank ended. In their place the bank of Ghana announced a new bank called the Consolidated Bank, as part...
3. Discuss the grave challenges facing planning practice in urban and regional settings of Ghana and...
3. Discuss the grave challenges facing planning practice in urban and regional settings of Ghana and propose some policy measures to reduce these challenges.
The Clearwater National Bank is planning to set up a new branch.This new branch is...
The Clearwater National Bank is planning to set up a new branch. This new branch is anticipated to generate 5 percent of the total business of the bank after it is opened. The bank also expects the return for this branch to be 15 percent with a standard deviation of 5 percent. Currently the bank has a 10 percent rate of return with a standard deviation of 5 percent. The correlation between the bank's current return and returns on the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT