The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...

The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year:


1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Units to be produced 10,000 9,000 11,000 12,000


Each unit requires 0.20 direct labor-hours and direct laborers are paid $12.00 per hour.

In addition, the variable manufacturing overhead rate is $1.50 per direct labor-hour. The fixed manufacturing overhead is $80,000 per quarter. The only noncash element of manufacturing overhead is depreciation, which is $20,000 per quarter.


Required:

1. Prepare the company’s direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced. (Round "Direct labor time per unit (hours)" and "Direct labor cost per hour" answers to 2 decimal places.)


2. Prepare the company’s manufacturing overhead budget.

Solutions

Expert Solution

1.Direct labour budget:

1st quarter 2nd quarter 3rd quarter 4th quarter year
Units to be produced 10,000 9,000 11,000 12,000 42,000
direct labour time per unit 0.20 0.20 0.20 0.20 0.20
total direct labour hours needed 2,000 1,800 2,200 2,400 8,400
direct labour cost per hour $12.00 12.00 12.00 12.00 12.00
total direct labour cost $24,000 $21,600 $26,400 $28,800 $100,800

2.manufacturing overhead budget:

1st quater 2nd quarter 3rd quarter 4th quarter year
bugeted direct labour hours (from above) 2,000 1,800 2,200 2,400 8,400
variable overhead rate $1.50 $1.50 1.50 1.50 1.50
variable manufacturing overhead 3,000 2,700 3,300 3,600 12,600
fixed manufacturing overhead 80,000 80,000 80,000 80,000 320,000
total manufacturing overhead 83,000 82,700 83,300 83,600 332,600
less:depreciation (20,000) (20,000) (20,000) (20,000) (80,000)
cash disbursements for manufacturing overhead 63,000 62,700 63,300 63,600 252,600

Related Solutions

The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,600 10,600 12,600 13,600 Each unit requires 0.20 direct labor-hours and direct laborers are paid $15.00 per hour. In addition, the variable manufacturing overhead rate is $1.75 per direct labor-hour. The fixed manufacturing overhead is $96,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 10,700 9,700 11,700 12,700 Each unit requires 0.25 direct labor-hours and direct laborers are paid $13.00 per hour. In addition, the variable manufacturing overhead rate is $1.80 per direct labor-hour. The fixed manufacturing overhead is $87,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,000 10,000 12,000 13,000 Each unit requires 0.30 direct labor-hours and direct laborers are paid $12.50 per hour. In addition, the variable manufacturing overhead rate is $2.05 per direct labor-hour. The fixed manufacturing overhead is $90,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,600 10,600 12,600 13,600 Each unit requires 0.20 direct labor-hours and direct laborers are paid $15.00 per hour. In addition, the variable manufacturing overhead rate is $1.75 per direct labor-hour. The fixed manufacturing overhead is $96,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,900 10,900 12,900 13,900 Each unit requires 0.20 direct labor-hours and direct laborers are paid $15.00 per hour. In addition, the variable manufacturing overhead rate is $1.50 per direct labor-hour. The fixed manufacturing overhead is $99,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,200 10,200 12,200 13,200 Each unit requires 0.25 direct labor-hours and direct laborers are paid $13.00 per hour. In addition, the variable manufacturing overhead rate is $1.40 per direct labor-hour. The fixed manufacturing overhead is $92,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st quarter 2nd quarter 3rd quarter 4th quarter units to be produced 11,600 10,600 12,600 13,600 Each unit requires 0.20 direct labor-hours and direct laborers are paid $15.00 per hour. In addition, the variable manufacturing overhead rate is $1.75 per direct labor-hour. The fixed manufacturing overhead is $96,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,700 10,700 12,700 13,700 Each unit requires 0.25 direct labor-hours and direct laborers are paid $15.00 per hour. In addition, the variable manufacturing overhead rate is $1.80 per direct labor-hour. The fixed manufacturing overhead is $97,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,100 10,100 12,100 13,100 Each unit requires 0.20 direct labor-hours and direct laborers are paid $12.50 per hour. In addition, the variable manufacturing overhead rate is $1.50 per direct labor-hour. The fixed manufacturing overhead is $91,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,100 10,100 12,100 13,100 Each unit requires 0.20 direct labor-hours and direct laborers are paid $12.50 per hour. In addition, the variable manufacturing overhead rate is $1.50 per direct labor-hour. The fixed manufacturing overhead is $91,000 per quarter. The only noncash element of manufacturing overhead...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT