In: Accounting
Q: Philips Company manufactures a variety of high- and low-volume products, including product 456, in its Westchester Plant. The following information pertains to the most recent year:
Total for product 456 |
Total for Westchester |
|
Unit-level overhead |
$200,000 |
|
Batch-level overhead |
300,000 |
|
Product-level overhead |
500,000 |
|
Plant-level overhead |
400,000 |
|
Total overhead |
$1,400,000 |
|
Units produced |
100 |
5,000 |
Direct labor hours |
200 |
20,000 |
Machine hours |
90 |
10,000 |
Setups |
6 |
120 |
Setup hours |
30 |
500 |
Design changes |
4 |
40 |
Design hours |
280 |
4,000 |
REQUIRED:
(1) If the Westchester Plant accumulates all overhead in a single cost pool and allocates it on the basis of machine hours, how much overhead cost will be allocated to a unit of Product 456?
(2) If the Westchester Plant uses ABC
with setups as the driver for all batch-level overhead, design
hours as the driver for all product-level overhead, and machine
hours as the driver for all unit- and plant-level overhead, how
much overhead cost will be allocated to a unit of Product
456?
1. Overhead cost allocated to a unit of Product 456 = Overhead rate * machine hours used
= 140 per machine hour * 90 machine hours
= $ 12,600
Overhead rate = Total overhead cost / Total Machine hours
= 1,400,000 / 10,000
= $ 140 per machine hour
2. Overhead cost allocated to a unit of Product 456 will be $ 55,400
Activity Rate | Activity by Product 456 | Cost allocated | |
Unit-level overhead | 20 per Machine hour | 90 | $ 1,800 |
Batch-level overhead | 2500 per setup | 6 | $ 15,000 |
Product-level overhead | 125 per Design hr | 280 | $ 35,000 |
Plant-level overhead | 40 per Machine hour | 90 | $ 3,600 |
$ 55,400 |
Activity | Activity Driver |
Activity Overhead (A) |
Cost Driver quantity (B) | Activity rate for each pool (A/B) |
Unit-level overhead | Machine hours | $ 200,000 | 10,000.00 | 20 per Machine hour |
Batch-level overhead | Setups | $ 300,000 | 120.00 | 2500 per setup |
Product-level overhead | Design hours | $ 500,000 | 4,000.00 | 125 per Design hr |
Plant-level overhead | Machine hours | $ 400,000 | 10,000.00 | 40 per Machine hour |