In: Operations Management
Create a schedule for the following data that starts June 1st 2016. Assume that one can work 7 days a week and 30 days a month.
Code |
Description |
Immediate |
Duration |
||
1 |
Strategic plan phase |
50 |
|||
2. |
Team formation |
70 |
|||
3 |
Master facility plan |
1,2 |
200 |
||
4. |
Space programming |
Finish with 3 |
240 |
||
a. Show a Gantt chart for the schedule. Make sure that the chart shows the time scale on quarterly basis.
b. Make sure that the chart shows the critical path. Create the chart and copy the chart into the word document (do not provide your project management files)
Step 1 :
Set Project Calender as all days working and days of working in month = 30
Step2: Set Project start date as 06/01/2016 in project information tab of MS project.
Step3: Enter the task details in MS Project Sheet with task name ,task duration and precedence as per details.
Gantt chart :
b)
Critical path of project is shown as red bar