Question

In: Accounting

18-1. Conditions of Performance The Caplans contract with Faithful Construction, Inc., to build a house for...

18-1. Conditions of Performance

The Caplans contract with Faithful Construction, Inc., to build a house for them for $360,000. The specifications state “all plumbing bowls and fixtures … to be Crane brand.” The Caplans leave on vacation, and during their absence, Faithful is unable to buy and install Crane plumbing fixtures. Instead, Faithful installs Kohler brand fixtures, an equivalent in the industry. On completion of the building contract, the Caplans inspect the work, discover the substitution, and refuse to accept the house, claiming Faithful has breached the conditions set forth in the specifications. Discuss fully the Caplans’ claim.(See Conditions.)

Answer this using the IRAC writing Format

I-Describe the issue at hand (the question being asked)

R-Describe the rule that is applicable in this situation

A-Apply the rule to the facts of yor situation

C-Draw a conclusion

Solutions

Expert Solution

Issue:

​The issue on hand in the case of Caplans Vs Faithful construction is fulfillment of conditions set out in the contract and whether a contract can be enforceable without fulfillment of conditions cited in the contract.

Rule:

​The rule is that all express conditions in a contract must be fulfilled. If the conditions are implied, then only substantial performace needs to be proved to make the contract enforceable.

Application:

If the specifications were considered to be expressed conditions to the contract, Faithful Constructions must perform them in full. The Caplans are not obligated to pay unless Faithful does so. If however, the conditions are implied, then Faithful will only need to prove substantial performance. However, he shall be l​iable for any damages which have occured due to him not performing the contract fully.In this case, the condition to install Crane fixtures is implied.

Conclusion:

​It is stated that the Kohler brand is equivalent to the Crane brand, thus substantial performance condition is met and the Caplans will be obligated to pay.If they have suffered monetary damages, they can deduct the amount after submission of proof.


Related Solutions

13–1. Conditions of Performance. The Caplans contract with Faithful Construction, Inc., to build a house for...
13–1. Conditions of Performance. The Caplans contract with Faithful Construction, Inc., to build a house for them for $360,000. The specifications state “all plumbing bowls and fixtures... to be Crane brand.” The Caplans leave on vacation, and during their absence, Faithful is unable to buy and install Crane plumbing fixtures. Instead, Faithful installs Kohler brand fixtures, an equivalent in the industry. On completion of the building contract, the Caplans inspect the work, discover the substitution, and refuse to accept the...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build...
Problem 18-09 Concord Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $891,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $260,580 $466,620 $618,000 Estimated costs to complete 345,420 139,380 –0– Progress billings to date 272,000 551,000 891,000 Cash collected...
1. In 20x1, Build Construction Corporation contracted to build a motel. The contract price is $600,000...
1. In 20x1, Build Construction Corporation contracted to build a motel. The contract price is $600,000 and the total cost is estimated as $400,000. Over the construction period there has been no change in either the contract price or the estimated total cost. Costs incurred for 20x1 and 20x2 are $200,000 and $160,000, respectively. How much gross profit should be recognized in 20x1 under the percentage-of-completion method? A) $80,000 B) $100,000 C) $120,000 D) $160,000 2.When using the percentage-of-completion method...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,075,000. During 2018, costs of $2,030,000 were incurred, with estimated costs of $4,030,000 yet to be incurred. Billings of $2,536,000 were sent, and cash collected was $2,280,000. In 2019, costs incurred were $2,536,000 with remaining costs estimated to be $3,645,000. 2019 billings were $2,786,000, and $2,505,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,540,000. During 2018, costs of $2,180,000 were incurred with estimated costs of $4,180,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT