In: Finance
A firm is evaluating a project with the following cash flow:
Year 0: -$28,000
Year 1: $12,000
Year 2: $15,000
Year 3: $11,000
A) If the required return is 14%, what is the NPV?
B) What is the IRR?
C) If the required return is 11%, using the NPV rule, should the firm accept the project?
D) What if the required return is 25%, should the firm accept the project?
Solution :
A) If the required return is 14%, what the NPV = $ 1,493.02
B) The IRR = 17.18 %
C) If the required return is 11%, the NPV = $ 3,028.25
Using the NPV Rule, the firm should accept the project, as the NPV is positive at $ 3,028.25
D) If the required return is 25% ,the NPV is = - $ 3,168
Using the NPV Rule, the firm should not accept the project, as the NPV is negative at $ 3168
Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.
,