In: Accounting
Note: I need a step by step answer to the question with an explanation of your answers:
White Corporation’s budget calls for the following sales for next year: Quarter 1 90,000 Quarter 3 68,000 Quarter 2 76,000 Quarter 4 96,000 Each unit of the product requires 3 pounds of direct materials. The company’s policy is to begin each quarter with an inventory of product equal to 5% of that quarter’s estimated sales requirements and an inventory of direct materials equal to 20% of that quarter’s estimated direct materials requirements of production. Required Determine the production and materials purchased budgets for the second quarter.
For the second quarter, following are the required data:
For clarification for the same, kindly go through the working notes
Working Notes:
Table Showing Calculation of Production and Direct Material Budgets
Quarter 1 | Quarter 2 | Quarter 3 | Quarter 4 | |
Sales Estimate | 90000 | 76000 | 68000 | 96000 |
Opening Balance of Finished Goods1 | (4500) | (3800) | (3400) | (4800) |
Closing Balance of Finished Goods2 | 3800 | 3400 | 4800 | 0* |
Production3 | 89300 | 75600 | 69400 | 91200 |
Direct Material Required4 | 267900 | 226800 | 208200 | 273600 |
Opening Balance of Direct Material5 | (53580) | (45360) | (41640) | (54720) |
Closing Balance of Direct Material6 | 45360 | 41640 | 54720 | 0* |
Direct Materials Purchased7 | 259680 | 223080 | 221280 | 218880 |
Footnotes:
1. Opening balance of Finished Goods = 5% of Sales estimated for the quarter
2. Closing Balance of Finished Goods = Opening Balance calculated for next quarter
3. Production = Sales Estimate + Opening balance of Finished Goods + Closing Balance of Finished Goods
Note: the correct formula should be Production = Sales Estimate - Opening balance of Finished Goods + Closing Balance of Finished Goods, but since the Opening Balance for finished goods has been presented as negative, we had to add it here.
4. Direct Material Required = Production X Direct Material used per unit [Given as 3 pounds]
5. Opening Balance of Direct Material = 20% of Direct Material required for the quarter
6. Closing Balance of Direct Material = Opening Balance calculated for next quarter
7. Direct Materials Purchased = Direct Material Required + Opening Balance of Direct Material + Closing Balance of Direct Material
Note: the correct formula should be Production = Sales Estimate - Opening balance of Direct Material + Closing Balance of Direct Material. but since the Opening balance for Direct Material has been presented as negative, we had to add it here.
* The Closing Balance for both, Finished Goods and Direct Material, in Quarter 4 has been assumed to be 0 since we have no way to calculate the same.