In: Operations Management
For x number of widgets to be produced,
Total time of machine A = Setup time + Run time = 2 + x/80 hours
Total cost using machine A = 40*total time = 40*(2+x/80) = 80+x/2
Total time of machine B = Setup time + Lubrication time + Run time = 30/60 + x/60 + (30/60)*x/(60*2)
= 0.5+x/48
Total cost using machine B = 40*total time = 40*(0.5+x/48) = 20+5x/6
Data for graph
EXCEL FORMULA:
Chart is drawn using the above data as follows:
In the above graph, we see that for number of widgets less than 170, Machine B gives the lowest total cost.
a)
150 is less than the range (1.e. 0 to 170)
Therefore, Machine B gives the least total cost
Answer: machine B
-------------------------------------------------------
b)
400 is greater than than the range (1.e. 0 to 170)
Therefore, Machine A gives the least total cost
Answer: machine A
-------------------------------------------------------
c)
The earliest point at which the costs will be same is computed by equating the total cost equations of both machines
80+x/2 = 20+5x/6
Solving for x, we get,
5x/6-x/2 = 80-20
x/3 = 60
x = 180
Answer: 180