Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the third plane took 18,000 hours to produce. Using an 85% learning curve and a $35-per-hour labor charge, he wants to determine the cost of the additional planes.
a) Time required for the fifth unit = ___________ hours (round your response to the nearest whole number).
b) Cost of the fifth unit = _______ dollars (round your response to the nearest whole number)
c) Time required for the sixth unit = __________ hours (round your response to the nearest whole number)
d) Cost of the sixth unit = ___________ dollars (round your response to the nearest whole number)
e) Time required for the seventh unit = _________ hours (round your response to the nearest whole number)
f) Cost of the seventh unit = ___________ dollars (round your response to the nearest whole number)
Learning Curve Equation = YX = KXS
Where,
Y = Required average for X
units/lot
K = Total time or cost required for 1st unit/lot
X =Units/lots whose average is required
S = Learning Curve Index
S = Log 0.85 ÷ Log 2 = (-0.07058107÷0.30103) = -0.2345
Average Time required for the first Four units = 18,000 hours . (4÷3)-0.2345
Average Time required for the first Four units = 16,826 hours
Average Time required for the first Five units = 18,000 hours . (5÷3)-0.2345
Average Time required for the first Five units = 15,968 hours
(a) Time required for the Fifth units = Total time required for first five units - Total time required for first four units
Time required for the Fifth units = (15,968 hours per unit x 5 units) - (16,826 hours per unit x 4 units)
Time required for the Fifth units = 12,536 hours (Approx)
(b) Cost of the fifth unit = 12,536 hours x $ 35 per hour
Cost of the fifth unit = $438,760 (Approx)
Average Time required for the first Six units = 18,000 hours . (6÷3)-0.2345
Average Time required for the first Six units = 15,300 hours
(c) Time required for the Sixth units = Total time required for first six units - Total time required for first five units
Time required for the Sixth units = (15,300 hours per unit x 6 units) - (15,968 hours per unit x 5 units)
Time required for the Sixth units = 11,960 hours (Approx)
(d) Cost of the sixth unit = 11,960 hours x $ 35 per hour
Cost of the sixth unit = $418,600 (Approx)
Average Time required for the first Seven units = 18,000 hours . (7÷3)-0.2345
Average Time required for the first Seven units = 14,757 hours
(e) Time required for the Seventh units = Total time required for first seven units - Total time required for first six units
Time required for the Seventh units = (14,757 hours per unit x 7 units) - (15,300 hours per unit x 6 units)
Time required for the Seventh units = 11,499 hours (Approx)
(f) Cost of the seventh unit = 11,499 hours x $ 35 per hour
Cost of the seventh unit = $402,465 (Approx)