examine the structure of the materials management processes for these types of items. Specifically, address the following:
What are some necessary considerations when designing a materials management process for bulk and long-lead time items?
How should a project schedule deal with these types of items?
Necessary conditions are:
- The quality and suitability of materials used for production
purposes are checked by technical department. The Tech department
takes advice from production department and work with them to
achieve this. While purchasing the dept. also looks at the economic
consideration of quality. They are checked for long-term basis
usage and if the product can be purchased continuously.
The seller should be then properly educated about the product so
that he/she can supply it properly.
The right product must be purchased at the right price. Proper
planning and negotiation must be done to get the right price.
The buyer also needs to get the right time for the purchase and
also the right quantity should be purchased.
Project schedule helps to have a check on inventory and to
properly schedule the availability of a long lead time item and
hence the engineer can know the procurement time and can also
adjust the plans accordingly.
Hence no problem of inventory and work happens and the workers can
continue with other scheduled works until the item is
delivered.